When the time taken to complete a given amount of work increases, then,
power increases
power decreases
energy increases
energy decreases
The correct Answer is:B
To solve the question, "When the time taken to complete a given amount of work increases, then," we need to analyze the relationship between work, time, and power.
1. Understanding the Concepts:
- Work (W) is defined as the amount of energy transferred when a force is applied over a distance.
- Power (P) is defined as the rate at which work is done. It can be mathematically expressed as:
P=Wt
where W is work done and t is the time taken to do that work.
2. Given Information:
- We are told that the amount of work is constant.
- The time taken to complete this work is increasing.
3. Analyzing the Effect of Increasing Time:
- If the time t increases while the work W remains constant, we can substitute this into the power formula:
P=Wt
- As t increases, the denominator of the fraction increases, which means that the overall value of P (power) must decrease.
4. Conclusion:
- Therefore, when the time taken to complete a given amount of work increases, the power decreases.
Final Answer:
- The correct option is: Power decreases.
- Work (W) is defined as the amount of energy transferred when a force is applied over a distance.
- Power (P) is defined as the rate at which work is done. It can be mathematically expressed as:
P=Wt
where W is work done and t is the time taken to do that work.
- We are told that the amount of work is constant.
- The time taken to complete this work is increasing.
- If the time t increases while the work W remains constant, we can substitute this into the power formula:
P=Wt
- As t increases, the denominator of the fraction increases, which means that the overall value of P (power) must decrease.
- Therefore, when the time taken to complete a given amount of work increases, the power decreases.
- The correct option is: Power decreases.
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
If B can do three-fourth of a work in 3 days, then the time taken to complete the whole work is ____.
A6 daysB5 daysC4 daysD3 days - Question 2 - Select One
If B can do three-fourth of a work in 3 days, then the time taken to complete the whole work is ____.
A6 daysB5 daysC4 daysD3 days - Question 3 - Select One
Assertion : Time taken by a body to complete a given work has nothing to do with energy of the body.
Reason : Because power of a body is the rate of doing work.AIf both, Assertion and Reason are true and Reason is correct explantion of Assertion.BIf both, Assertion and Reason are true but Reason is not a correct explanation of the Assertion.CIf Assertion is true but the Reason is false.DIf both, Assertion and Reason are false.
For a first order reaction, calculate the ratio between the time taken to complete three fourth of the reaction and the time taken to complete half of the reaction.
View SolutionIn the following questions, which of them vary directly and which vary inversely with each other and which are neither of the two?
(i) The time taken by a train to cover a fixed distance and the speed of the train.
(ii) The distance travelled by CNG bus and the amount of CNG used.
(iii) The number of people working and the time to complete a given work.
(iv) Income tax and the income
(v) Distance travelled by an auto-rickshaw and time takenView SolutionFifteen men take 30 days to complete a piece of work, working 8 hours a day. Find the time taken by 30 men to complete 5 times as much work, working 10 hours a day.
View SolutionFifteen men take 30 days to complete a piece of work, working 8 hours a day. Find the time taken by 30 men to complete 5 times as much work, working 10 hours a day.
View SolutionThe amount of work in a leather factory is increased by 50%. By what percent is it necessary to increase the number of workers to complete the new amount of work in previously planned time , if the productivity of the new labour is 25% more.
View Solution