150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:25 days


Suppose the work is completed in n days. Since 4 workers dropped every day except the first day, the total amount of work done in n days is the sum of n terms of an A.P. with first term 150 and common difference -4.
Total amount of work done
=n2[2×150+(n1)×(4)]=n(1522n)
Had the workers not dropped, the work would have finished in (n-8) days with 150 workers working each day. Therefore, the total amount of work done in n days is 150 (n-8).
n(152-2n)=150(n-8)
n2n600=0
(n25)(n+24)=0
n=25
Thus, the work is completed in 25 days

Updated on:21/07/2023
|


Topper's Solved these Questions


Similar Questions