150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.
The correct Answer is:25 days
Suppose the work is completed in n days. Since 4 workers dropped every day except the first day, the total amount of work done in n days is the sum of n terms of an A.P. with first term 150 and common difference -4.
∴ Total amount of work done
=n2[2×150+(n−1)×(−4)]=n(152−2n)
Had the workers not dropped, the work would have finished in (n-8) days with 150 workers working each day. Therefore, the total amount of work done in n days is 150 (n-8).
∴ n(152-2n)=150(n-8)
⇒n2−n−600=0
⇒(n−25)(n+24)=0
⇒n=25
Thus, the work is completed in 25 days
Topper's Solved these Questions
- PROGRESSION AND SERIESBOOK - CENGAGE ENGLISHCHAPTER - PROGRESSION AND SERIESEXERCISE - CONCEPT APPLICATION EXERICISE 5.4
13 Videos
- PROGRESSION AND SERIESBOOK - CENGAGE ENGLISHCHAPTER - PROGRESSION AND SERIESEXERCISE - CONCEPT APPLICATION EXERICISE 5.5
10 Videos
- PROGRESSION AND SERIESBOOK - CENGAGE ENGLISHCHAPTER - PROGRESSION AND SERIESEXERCISE - CONCEPT APPLICATION EXERICISE 5.2
10 Videos
- PROBABILITY IIBOOK - CENGAGE ENGLISHCHAPTER - PROBABILITY IIEXERCISE - MULTIPLE CORRECT ANSWER TYPE
6 Videos
- PROPERTIES AND SOLUTIONS OF TRIANGLEBOOK - CENGAGE ENGLISHCHAPTER - PROPERTIES AND SOLUTIONS OF TRIANGLEEXERCISE - Archives (Numerical Value Type)
3 Videos
Similar Questions
About 150 workers were engaged to finish a piece of work in a certain number of days. Four workers stopped working on the second day, four more workers stopped their work on the third day and so on. It took 8 more days to finish the work. Then the number of days in which the work was completed is 29 days b. 24 days c. 25 days d. none of these
View SolutionIn a factory, 150 workers were engaged to finish a piece of work in a certain number of days. However, if 4 workers are dropped everyday, except the first day, it will take 8 more days to finish the work. Find the number of days in which the work was to be completed.
View SolutionA can do 14 of a work in 5 days and B can do 13 of the same work in 10 days. Find the number of days in which both working together will complete the work.
View SolutionAnil can do a piece of work in 5 days and ankur in 4 days. How long will they take to do the same work, if they work together?
View SolutionA and B can finish a piece of work in 12 days, B and C in 15 days shile C and A in 20 days. How long will they take to finish it together ? How long will each take to finish the work alone ?
View Solution12 men can finish a piece of work in 25 days. The number of days in which the same piece of work can be done by 20 men, is
(a) 10 days
(b) 12 days
(c) 15 days
(d) 14 days
View SolutionA can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work ?
View SolutionIf 8 men can do a piece of work in 15 days, how many men are required to do the same piece of work in 10 days ?
View Solution40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?
View SolutionA daily wage worker works for 23 days in a month. He gets Rs 400 per working day. However, his supervisor is very strict and fines him Rs 100 for each day he arrives late to work. If at the end of the 23 days, the worker has earned Rs 8000, find out the number of days he reached for work on time and the number of days he was late.
View Solution