About 150 workers were engaged to finish a piece of work in a certain number of days. Four workers stopped working on the second day, four more workers stopped their work on the third day and so on. It took 8 more days to finish the work. Then the number of days in which the work was completed is 29 days b. 24 days c. 25 days d. none of these
To solve the problem step by step, let's denote the following:
- Let k be the initial number of days required to complete the work with 150 workers.
- The work done by one worker in a day is denoted as t.
Step 1: Calculate the total work
The total work can be expressed as:
Total Work=Number of Workers×Work done by one worker in a day×Number of Days
Thus, we have:
Total Work=150×t×k
Step 2: Determine the number of workers each day
On the second day, 4 workers stop working, and this pattern continues. Therefore, the number of workers on each day is:
- Day 1: 150 workers
- Day 2: 146 workers
- Day 3: 142 workers
- ...
- Day i: 150−4(i−1) workers
Step 3: Calculate the total work done over k+8 days
Since it took 8 more days to finish the work, the total number of days worked is k+8. The work done in these days can be expressed as:
Total Work=150t+146t+142t+…+(150−4(k+8−1))t
This sequence is an arithmetic progression (AP) where:
- First term a=150t
- Common difference d=−4t
- Number of terms n=k+8
Step 4: Sum of the arithmetic progression
The sum Sn of the first n terms of an AP is given by:
Sn=n2(2a+(n−1)d)
Substituting the values:
Sk+8=k+82(2×150t+(k+7)(−4t))
This simplifies to:
Sk+8=k+82(300t−4t(k+7))
=k+82(300t−4tk−28t)
=k+82((272−4k)t)
Step 5: Set the total work equations equal
Equating the total work expressions:
150kt=(k+8)(272−4k)t2
Dividing both sides by t (assuming t≠0):
150k=(k+8)(272−4k)2
Multiplying through by 2:
300k=(k+8)(272−4k)
Step 6: Expand and simplify
Expanding the right side:
300k=272k+2176−4k2−32k
Combining like terms gives:
300k=240k+2176−4k2
Rearranging leads to:
4k2+60k−2176=0
Step 7: Solve the quadratic equation
Using the quadratic formula k=−b±√b2−4ac2a:
k=−60±√602−4⋅4⋅(−2176)2⋅4
Calculating the discriminant:
=−60±√3600+348168
=−60±√384168
=−60±1968
Calculating the two possible values for k:
1. k=1368=17
2. k=−2568 (not valid since k must be positive)
Thus, k=17.
Step 8: Calculate the total days taken
Since it took 8 more days:
Total Days=k+8=17+8=25
Final Answer
The number of days in which the work was completed is 25 days (Option c).
---
- The work done by one worker in a day is denoted as t.
The total work can be expressed as:
Total Work=Number of Workers×Work done by one worker in a day×Number of Days
Thus, we have:
Total Work=150×t×k
On the second day, 4 workers stop working, and this pattern continues. Therefore, the number of workers on each day is:
- Day 1: 150 workers
- Day 2: 146 workers
- Day 3: 142 workers
- ...
- Day i: 150−4(i−1) workers
Since it took 8 more days to finish the work, the total number of days worked is k+8. The work done in these days can be expressed as:
Total Work=150t+146t+142t+…+(150−4(k+8−1))t
This sequence is an arithmetic progression (AP) where:
- First term a=150t
- Common difference d=−4t
- Number of terms n=k+8
The sum Sn of the first n terms of an AP is given by:
Sn=n2(2a+(n−1)d)
Substituting the values:
Sk+8=k+82(2×150t+(k+7)(−4t))
This simplifies to:
Sk+8=k+82(300t−4t(k+7))
=k+82(300t−4tk−28t)
=k+82((272−4k)t)
Equating the total work expressions:
150kt=(k+8)(272−4k)t2
Dividing both sides by t (assuming t≠0):
150k=(k+8)(272−4k)2
Multiplying through by 2:
300k=(k+8)(272−4k)
Expanding the right side:
300k=272k+2176−4k2−32k
Combining like terms gives:
300k=240k+2176−4k2
Rearranging leads to:
4k2+60k−2176=0
Using the quadratic formula k=−b±√b2−4ac2a:
k=−60±√602−4⋅4⋅(−2176)2⋅4
Calculating the discriminant:
=−60±√3600+348168
=−60±√384168
=−60±1968
Calculating the two possible values for k:
1. k=1368=17
2. k=−2568 (not valid since k must be positive)
Since it took 8 more days:
Total Days=k+8=17+8=25
The number of days in which the work was completed is 25 days (Option c).
Topper's Solved these Questions
Similar Questions
150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.
View SolutionIn a factory, 150 workers were engaged to finish a piece of work in a certain number of days. However, if 4 workers are dropped everyday, except the first day, it will take 8 more days to finish the work. Find the number of days in which the work was to be completed.
View SolutionA can do a piece of work in 10 days and B in 15 days. How long will they take to finish it working together ?
View SolutionA can do 14 of a work in 5 days and B can do 13 of the same work in 10 days. Find the number of days in which both working together will complete the work.
View Solution12 men can finish a piece of work in 25 days. The number of days in which the same piece of work can be done by 20 men, is
(a) 10 days
(b) 12 days
(c) 15 days
(d) 14 days
View SolutionRakesh can do piece of work in 20 days. How much work can be do in 4 days?
View SolutionAnil can do a piece of work in 5 days and ankur in 4 days. How long will they take to do the same work, if they work together?
View SolutionIf 52 men can do a piece of work in 35 days in how many days 28 men will do it ?
View SolutionIf 12 women can do a piece of work in 9 days, in how many days can 18 women do it ?
View Solution8 men can finish a piece of work in 40 days. If 2 more men join them, the work will be computed in
(a) 30 days
(b) 32 days
(c) 36 days
(d) 25 days
View Solution