About 150 workers were engaged to finish a piece of work in a certain number of days. Four workers stopped working on the second day, four more workers stopped their work on the third day and so on. It took 8 more days to finish the work. Then the number of days in which the work was completed is 29 days b. 24 days c. 25 days d. none of these

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, let's denote the following:

- Let k be the initial number of days required to complete the work with 150 workers.
- The work done by one worker in a day is denoted as t.

Step 1: Calculate the total work
The total work can be expressed as:
Total Work=Number of Workers×Work done by one worker in a day×Number of Days
Thus, we have:
Total Work=150×t×k

Step 2: Determine the number of workers each day
On the second day, 4 workers stop working, and this pattern continues. Therefore, the number of workers on each day is:
- Day 1: 150 workers
- Day 2: 146 workers
- Day 3: 142 workers
- ...
- Day i: 1504(i1) workers

Step 3: Calculate the total work done over k+8 days
Since it took 8 more days to finish the work, the total number of days worked is k+8. The work done in these days can be expressed as:
Total Work=150t+146t+142t++(1504(k+81))t
This sequence is an arithmetic progression (AP) where:
- First term a=150t
- Common difference d=4t
- Number of terms n=k+8

Step 4: Sum of the arithmetic progression
The sum Sn of the first n terms of an AP is given by:
Sn=n2(2a+(n1)d)
Substituting the values:
Sk+8=k+82(2×150t+(k+7)(4t))
This simplifies to:
Sk+8=k+82(300t4t(k+7))
=k+82(300t4tk28t)
=k+82((2724k)t)

Step 5: Set the total work equations equal
Equating the total work expressions:
150kt=(k+8)(2724k)t2
Dividing both sides by t (assuming t0):
150k=(k+8)(2724k)2
Multiplying through by 2:
300k=(k+8)(2724k)

Step 6: Expand and simplify
Expanding the right side:
300k=272k+21764k232k
Combining like terms gives:
300k=240k+21764k2
Rearranging leads to:
4k2+60k2176=0

Step 7: Solve the quadratic equation
Using the quadratic formula k=b±b24ac2a:
k=60±60244(2176)24
Calculating the discriminant:
=60±3600+348168
=60±384168
=60±1968
Calculating the two possible values for k:
1. k=1368=17
2. k=2568 (not valid since k must be positive)

Thus, k=17.

Step 8: Calculate the total days taken
Since it took 8 more days:
Total Days=k+8=17+8=25

Final Answer
The number of days in which the work was completed is 25 days (Option c).

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions