16 persons can reap 1/5th field in 6 days. How many persons (with same efficiency) are required to reap rest of the field in 8 days?
27
54
48
64
The correct Answer is:C
To solve the problem step by step, we can follow these calculations:
Step 1: Determine the total work done by 16 persons in 6 days
Given that 16 persons can reap 1/5 of the field in 6 days, we can calculate the total work done in terms of "man-days."
Total work done by 16 persons in 6 days:
Work=Number of persons×Number of days=16 persons×6 days=96 man-days
This means that 96 man-days are required to reap 1/5 of the field.
Step 2: Calculate the total work required for the entire field
Since 1/5 of the field requires 96 man-days, the total work required for the entire field (5/5) can be calculated as follows:
Total Work=96 man-days×5=480 man-days
Step 3: Determine the remaining work to be done
Since 1/5 of the field has already been completed, the remaining work is:
Remaining Work=480 man-days−96 man-days=384 man-days
Step 4: Calculate the number of persons required to complete the remaining work in 8 days
Let m be the number of persons required to complete the remaining 384 man-days of work in 8 days. We can set up the equation:
m persons×8 days=384 man-days
Solving for m:
m=384 man-days8 days=48 persons
Final Answer
Thus, the number of persons required to reap the rest of the field in 8 days is 48 persons.
---
Given that 16 persons can reap 1/5 of the field in 6 days, we can calculate the total work done in terms of "man-days."
Work=Number of persons×Number of days=16 persons×6 days=96 man-days
This means that 96 man-days are required to reap 1/5 of the field.
Since 1/5 of the field requires 96 man-days, the total work required for the entire field (5/5) can be calculated as follows:
Total Work=96 man-days×5=480 man-days
Since 1/5 of the field has already been completed, the remaining work is:
Remaining Work=480 man-days−96 man-days=384 man-days
Let m be the number of persons required to complete the remaining 384 man-days of work in 8 days. We can set up the equation:
m persons×8 days=384 man-days
Solving for m:
m=384 man-days8 days=48 persons
Thus, the number of persons required to reap the rest of the field in 8 days is 48 persons.
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
16 persons can reap 1/5th field in 6 days. How many persons (with same efficiency) are required to reap rest of the field in 8 days?
A27B54C48D64 - Question 2 - Select One
30 persons can reap a field in 17 days. How many more persons should be engaged to reap the same field in 10 days?
A17B30C51D21 - Question 3 - Select One
35 men can reap a field in 8 days. In how many days can 20 men reap it?
A14 dayB28 dayC8712 dayDnon of these
45 cows can graze a field in 13 days. How many cows will graze the same field in 9 days?
View Solution45 cows can graze a field in 13 days. How many cows will gråze the same field in 9 days?
View Solution12 persons can do a piece of work in 4 days. How many persons are required to complete 8 times the work in half the time?
View SolutionIf 16 men can reap a field in 30 days.in how many days will 20 men reap the same field?
View SolutionIf 16 men can reap a field in 30 days.in how many days will 20 men reap the same field?
View Solution