12 persons can do a piece of work in 4 days. How many persons are required to complete 8 times the work in half the time?
192
190
180
144
The correct Answer is:A
To solve the problem step by step, let's break it down:
Step 1: Understand the initial work scenario
We know that 12 persons can complete 1 piece of work in 4 days.
Step 2: Calculate the total work in person-days
The total work can be calculated in terms of person-days:
- Total work = Number of persons × Number of days
- Total work = 12 persons × 4 days = 48 person-days
Step 3: Determine the new work scenario
We need to complete 8 times the work in half the time:
- New work = 8 × 1 = 8 pieces of work
- New time = 4 days / 2 = 2 days
Step 4: Calculate the total work required for the new scenario
Now, we calculate the total work in person-days for the new scenario:
- Total work required = 8 pieces of work × 48 person-days (from Step 2)
- Total work required = 8 × 48 = 384 person-days
Step 5: Calculate the number of persons required
Now we need to find out how many persons are required to complete 384 person-days of work in 2 days:
- Let the number of persons required be P.
- We know that P persons working for 2 days should equal the total work required.
- Therefore, P×2days=384person−days
Step 6: Solve for P
To find P:
- P=3842=192
Conclusion
Thus, 192 persons are required to complete 8 times the work in half the time.
---
We know that 12 persons can complete 1 piece of work in 4 days.
The total work can be calculated in terms of person-days:
- Total work = Number of persons × Number of days
- Total work = 12 persons × 4 days = 48 person-days
We need to complete 8 times the work in half the time:
- New work = 8 × 1 = 8 pieces of work
- New time = 4 days / 2 = 2 days
Now, we calculate the total work in person-days for the new scenario:
- Total work required = 8 pieces of work × 48 person-days (from Step 2)
- Total work required = 8 × 48 = 384 person-days
Now we need to find out how many persons are required to complete 384 person-days of work in 2 days:
- Let the number of persons required be P.
- We know that P persons working for 2 days should equal the total work required.
- Therefore, P×2days=384person−days
To find P:
- P=3842=192
Thus, 192 persons are required to complete 8 times the work in half the time.
Topper's Solved these Questions
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TEST YOURSELF25videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-V19videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND DISTANCEEXERCISE - Type -XI74videos
TIME AND DISTANCE
- BOOK - KIRAN PUBLICATIONCHAPTER - TRIGONOMETRY EXERCISE - TEST YOURSELF25videos
TRIGONOMETRY
Similar Questions
Knowledge Check
- Question 1 - Select One
15 persons can do a piece of work in 12 days. How many more people are required to complete the work in 10 days?
A4B5C3Dnone of these - Question 2 - Select One
30 persons can do a piece of work in 24 days. How many more people are required to complete the work in 20 days?
A4B5C6Dnone of these - Question 3 - Select One
Twelve persons can do a piece of work in 20 days. How many persons are required to do the same in 24 days?
A20B10C15D18
Two persons can complete a piece of work in 9 days. How many more persons are needed to complete double the work in 12 days?
View SolutionTwelve men can do a piece of work in 15 days. How many men are required to complete a work which is three and a half times the original work in 10 days ?
View SolutionTwelve men can do a piece of work in 15 days. How many men are required to complete a work which is three and a half times the original work in 10 days ?
View SolutionTwelve men can do a piece of work in 15 days. How many men are required to complete a work which is three and a half times the original work in 10 days ?
View Solution36 personn working 8 hours a day can do 3 units of working in 12 days. How many persons are required to complete 4 units of that work, if they work 6 hours a day for 16 days?
View Solution