Doubtnut Promotions Sticky

A, B and C can do a piece of work in 12, 15 and 20 days. How much minimum time should be required to complete this work if more than two persons can not work in a day and in any two consecutive days same pair can not work ?

A

623

B

7117

C

8

D

9

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:7 days


To solve the problem, we need to determine how much minimum time is required to complete the work given the constraints. Let's break down the solution step by step.

Step 1: Determine the work done by A, B, and C
- A can complete the work in 12 days, so A's work per day = 112.
- B can complete the work in 15 days, so B's work per day = 115.
- C can complete the work in 20 days, so C's work per day = 120.

Step 2: Find the least common multiple (LCM) of the days
To find a common basis for the work, we can assume the total work to be the LCM of 12, 15, and 20.
- LCM of 12, 15, and 20 = 60.

Step 3: Calculate the efficiency of A, B, and C
- A's efficiency = 6012=5 units of work per day.
- B's efficiency = 6015=4 units of work per day.
- C's efficiency = 6020=3 units of work per day.

Step 4: Determine the work done in two consecutive days
Since more than two persons cannot work in a day and the same pair cannot work on consecutive days, we can have the following pairs:
1. Day 1: A and B
2. Day 2: A and C

Calculating the work done:
- Work done by A and B in one day = 5+4=9 units.
- Work done by A and C in the next day = 5+3=8 units.

Step 5: Total work done in two days
- Total work done in two days = Work done on Day 1 + Work done on Day 2 = 9+8=17 units.

Step 6: Calculate the number of days required to finish the work
- Total work = 60 units.
- Work done in 2 days = 17 units.
- Total number of 2-day cycles needed = 6017.

Step 7: Calculate the total time
- The number of complete 2-day cycles = 6017 which is approximately 3.529 cycles.
- This means we need 3 complete cycles (6 days) and then some additional work on the 7th day.

Step 8: Calculate remaining work after 3 cycles
- Work done in 3 cycles = 3×17=51 units.
- Remaining work = 6051=9 units.

Step 9: Determine the work done on the 7th day
- On the 7th day, we can use A and B again (as they are not the same pair as the last day).
- A and B can do 9 units of work in one day, which is enough to complete the remaining work.

Conclusion
Thus, the total time required to complete the work is 6+1=7 days.

Final Answer
The minimum time required to complete the work is 7 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    15 persons can do a piece of work in 12 days. How many more people are required to complete the work in 10 days?

    A4
    B5
    C3
    Dnone of these
  • Question 2 - Select One

    30 persons can do a piece of work in 24 days. How many more people are required to complete the work in 20 days?

    A4
    B5
    C6
    Dnone of these
  • Question 3 - Select One

    If 40 persons can do a piece of work in 14 days, then the number of persons required to complete the work in 28 days.

    A40
    B20
    C14
    D10