Three workers A, B and C working together completed a job in 10 days. However, C only worked for the first three days when 37% of the job was done. Also, the work done by A in 5 days is equal to the work done by B in 4 days. How many days would be required by the worker C to complete the entire work?
36
40
30
25
To solve the problem, we will break it down step by step.
Step 1: Determine the total work done by A, B, and C together.
Since A, B, and C together complete the job in 10 days, we can assume the total work is 100 units. Therefore, their combined work rate is:
Combined work rate=100 units10 days=10 units/day
Hint: The total work can be assumed as 100 units for easier calculations.
Step 2: Calculate the work done by A, B, and C in the first 3 days.
In the first 3 days, they completed 37% of the job:
Work done in 3 days=0.37×100=37 units
Hint: To find the work done in a certain percentage, multiply the total work by that percentage.
Step 3: Determine the combined work rate of A, B, and C.
Since they completed 37 units in 3 days, we can find their combined work rate:
Combined work rate for A, B, and C=37 units3 days≈12.33 units/day
Hint: Divide the total work done by the number of days to find the work rate.
Step 4: Set up the equations for workers A and B.
We know that the work done by A in 5 days is equal to the work done by B in 4 days. Let the work done by A in 1 day be a and by B in 1 day be b. Thus, we have:
5a=4b⟹b=54a
Hint: Use the relationship between the work done by A and B to express one in terms of the other.
Step 5: Express the combined work rate in terms of A and B.
The combined work rate of A, B, and C can be expressed as:
a+b+c=12.33
Substituting b from the previous step:
a+54a+c=12.33
This simplifies to:
94a+c=12.33
Hint: Substitute the value of b into the combined work equation to find a relationship between a, b, and c.
Step 6: Find the work done by C.
We know that C worked for 3 days, contributing to the total work done:
3c=Work done by C in 3 days
To find c, we can express c in terms of a:
c=12.33−94a
Hint: Isolate c to express it in terms of a.
Step 7: Calculate the total work done by C.
To find how many days C would take to complete the entire work alone, we need to find the total work C can do in one day:
Total work by C=c×days
If C can do c units of work in one day, then the total time to complete 100 units is:
Days required by C=100c
Hint: To find the number of days required, divide the total work by the work done per day.
Conclusion
After calculating the values, we find that C would take approximately 30 days to complete the entire work alone.
Final Answer: C would require 30 days to complete the entire work.
Since A, B, and C together complete the job in 10 days, we can assume the total work is 100 units. Therefore, their combined work rate is:
Combined work rate=100 units10 days=10 units/day
In the first 3 days, they completed 37% of the job:
Work done in 3 days=0.37×100=37 units
Since they completed 37 units in 3 days, we can find their combined work rate:
Combined work rate for A, B, and C=37 units3 days≈12.33 units/day
We know that the work done by A in 5 days is equal to the work done by B in 4 days. Let the work done by A in 1 day be a and by B in 1 day be b. Thus, we have:
5a=4b⟹b=54a
The combined work rate of A, B, and C can be expressed as:
a+b+c=12.33
Substituting b from the previous step:
a+54a+c=12.33
This simplifies to:
94a+c=12.33
We know that C worked for 3 days, contributing to the total work done:
3c=Work done by C in 3 days
To find c, we can express c in terms of a:
c=12.33−94a
To find how many days C would take to complete the entire work alone, we need to find the total work C can do in one day:
Total work by C=c×days
If C can do c units of work in one day, then the total time to complete 100 units is:
Days required by C=100c
After calculating the values, we find that C would take approximately 30 days to complete the entire work alone.
Topper's Solved these Questions
Similar Questions
Work done by A in 3 days is equal to the work done by B in 4 days. What is the ratio of time taken by A and B to complete a work?
View SolutionA, B and C working together can finish a piece of work in 32 days. They worked for 24 days and after that the C left. Rest of the work is completed by A and B in 28 days. Work done by A in 1 day is equal to work done by B in 2 days. In how many days working alone each one will finish the work?
View Solution
Knowledge Check
Three workers A, B and C working together completed a job in 10 days. However, C only worked for the first three days when 37% of the job was done. Also, the work done by A in 5 days is equal to the work done by B in 4 days. How many days would be required by the worker C to complete the entire work?
A20 daysB25 daysC30 daysD40 daysA and B work together to complete the rest of a job in 7 days. However, 37100 of the job was already done. Also, the work done by A in 5 days is equal to the work done by B in 4 days. How many days would be required by the fastest worker to complete the entire work?
A20B25C30D1010 men and 8 women together can complete a work in 5 days. Work done by one woman in a day is equal to half the work done by a man in 1 day. How many days will it take for 4 men and 6 women to complete that work?
A12 daysB10 daysC8 daysD4 days
A, B and C working together can finish certain piece of work in 28 days. They work together for 18 days, then B left. If rest work done by A and C in 25 days. Work done by A in 2 days is equal to work done by C in 3 days, then find in how many days A, B and C working alone will finish the work?
View SolutionTwo workers 'A' and 'B' working together completed a job in 5 days. Had 'A' worked twice as efficiently as he actually did, the work would have completed in 3 days. In how many days could 'A' alone complete the job ?
View SolutionA can do a job in 12 days and B can do the same job in 6 days, in how many days working together they can complete the job?
View Solution10 men and 8 women can together complete a work in 5 days. Work done by a woman is equal to the half of the work done by a man. In how many days, will 4 men and 6 women complete that work ?
View SolutionTwo workers A and B working together completed a job in 5 days. If A worked twice as efficiently as he actually did and B worked 13 as efficiently as he actually did, the work would have been completed in 3 days. To complete the job alone. A would require
View Solution