Doubtnut Promotions Sticky

Three workers A, B and C working together completed a job in 10 days. However, C only worked for the first three days when 37% of the job was done. Also, the work done by A in 5 days is equal to the work done by B in 4 days. How many days would be required by the worker C to complete the entire work?

A

36

B

40

C

30

D

25

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem, we will break it down step by step.

Step 1: Determine the total work done by A, B, and C together.
Since A, B, and C together complete the job in 10 days, we can assume the total work is 100 units. Therefore, their combined work rate is:
Combined work rate=100 units10 days=10 units/day

Hint: The total work can be assumed as 100 units for easier calculations.

Step 2: Calculate the work done by A, B, and C in the first 3 days.
In the first 3 days, they completed 37% of the job:
Work done in 3 days=0.37×100=37 units

Hint: To find the work done in a certain percentage, multiply the total work by that percentage.

Step 3: Determine the combined work rate of A, B, and C.
Since they completed 37 units in 3 days, we can find their combined work rate:
Combined work rate for A, B, and C=37 units3 days12.33 units/day

Hint: Divide the total work done by the number of days to find the work rate.

Step 4: Set up the equations for workers A and B.
We know that the work done by A in 5 days is equal to the work done by B in 4 days. Let the work done by A in 1 day be a and by B in 1 day be b. Thus, we have:
5a=4bb=54a

Hint: Use the relationship between the work done by A and B to express one in terms of the other.

Step 5: Express the combined work rate in terms of A and B.
The combined work rate of A, B, and C can be expressed as:
a+b+c=12.33
Substituting b from the previous step:
a+54a+c=12.33
This simplifies to:
94a+c=12.33

Hint: Substitute the value of b into the combined work equation to find a relationship between a, b, and c.

Step 6: Find the work done by C.
We know that C worked for 3 days, contributing to the total work done:
3c=Work done by C in 3 days
To find c, we can express c in terms of a:
c=12.3394a

Hint: Isolate c to express it in terms of a.

Step 7: Calculate the total work done by C.
To find how many days C would take to complete the entire work alone, we need to find the total work C can do in one day:
Total work by C=c×days
If C can do c units of work in one day, then the total time to complete 100 units is:
Days required by C=100c

Hint: To find the number of days required, divide the total work by the work done per day.

Conclusion
After calculating the values, we find that C would take approximately 30 days to complete the entire work alone.

Final Answer: C would require 30 days to complete the entire work.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Three workers A, B and C working together completed a job in 10 days. However, C only worked for the first three days when 37% of the job was done. Also, the work done by A in 5 days is equal to the work done by B in 4 days. How many days would be required by the worker C to complete the entire work?

    A20 days
    B25 days
    C30 days
    D40 days
  • Question 2 - Select One

    A and B work together to complete the rest of a job in 7 days. However, 37100 of the job was already done. Also, the work done by A in 5 days is equal to the work done by B in 4 days. How many days would be required by the fastest worker to complete the entire work?

    A20
    B25
    C30
    D10
  • Question 3 - Select One

    10 men and 8 women together can complete a work in 5 days. Work done by one woman in a day is equal to half the work done by a man in 1 day. How many days will it take for 4 men and 6 women to complete that work?

    A12 days
    B10 days
    C8 days
    D4 days