Doubtnut Promotions Sticky

25 men can complete a work in 10 days. 20 boys can complete this work in 50 days. 5 men start the work and aftr 10 days 10 boys joined them and remaining work is completed in 20 days. How many boys are joined ?

A

20

B

15

C

10

D

30

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will first determine the efficiency of men and boys, calculate the total work, and then analyze how the work was completed.

Step 1: Determine the efficiency of men and boys
- Given: 25 men can complete the work in 10 days.
- Total work (W) can be calculated as:
W=Number of men×Days=25×10=250 man-days
- Efficiency of 1 man (m):
Efficiency of 1 man=WTotal men=25025=10 units/day

- Given: 20 boys can complete the work in 50 days.
- Total work (W) can also be calculated as:
W=Number of boys×Days=20×50=1000 boy-days
- Efficiency of 1 boy (b):
Efficiency of 1 boy=WTotal boys=100020=50 units/day

Step 2: Find the ratio of efficiencies
- From the calculations:
Efficiency of 1 man=10 units/day
Efficiency of 1 boy=50 units/day
- The ratio of efficiency of men to boys is:
mb=1050=15

Step 3: Calculate the total work
- Total work done is 1000 units (as calculated from boys) or 250 man-days (as calculated from men). Both give the same total work of 1000 units.

Step 4: Work done by 5 men in 10 days
- 5 men work for 10 days:
Work done by 5 men=5 men×10 days×10 units/day=500 units

Step 5: Remaining work
- Remaining work after 10 days:
Remaining work=1000500=500 units

Step 6: Work done after 10 boys join
- After 10 boys join, the total workforce consists of 5 men and 10 boys.
- Efficiency of 5 men:
5 men×10 units/day=50 units/day
- Efficiency of 10 boys:
10 boys×50 units/day=500 units/day
- Total efficiency after boys join:
Total efficiency=50+500=550 units/day

Step 7: Time taken to complete remaining work
- The remaining work of 500 units is completed in 20 days:
Work done in 20 days=550 units/day×20 days=11000 units
- Since they only needed to complete 500 units, this confirms that the calculations are consistent.

Step 8: Calculate how many boys joined
- Let x be the number of boys who joined after 10 days.
- We know that the total work done in 20 days is:
20×(5 men×10+x boys×50)=500
- Setting up the equation:
20×(50+50x)=500
1000+1000x=500
1000x=5001000
x=20

Conclusion
- Therefore, the number of boys who joined is 20.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?

    A40
    B42
    C38
    D32
  • Question 2 - Select One

    15 men can complete a work in 10 days while 20 boys can complete the same work in 15 days How many days will 10 men and 10 boys together take to complete the same work ?

    A10 days
    B8 days
    C12 days
    D9 days
  • Question 3 - Select One

    A can complete a work in 25 days, B can complete the same work in 20 days. If they work together for 10 days and remaining work is completed by C alone in 10 days. In how many days A, B, and C together can complete the same task?

    A12 days
    B15 days
    C10 days
    D8 days