25 men can complete a work in 10 days. 20 boys can complete this work in 50 days. 5 men start the work and aftr 10 days 10 boys joined them and remaining work is completed in 20 days. How many boys are joined ?
20
15
10
30
To solve the problem step by step, we will first determine the efficiency of men and boys, calculate the total work, and then analyze how the work was completed.
Step 1: Determine the efficiency of men and boys
- Given: 25 men can complete the work in 10 days.
- Total work (W) can be calculated as:
W=Number of men×Days=25×10=250 man-days
- Efficiency of 1 man (m):
Efficiency of 1 man=WTotal men=25025=10 units/day
- Given: 20 boys can complete the work in 50 days.
- Total work (W) can also be calculated as:
W=Number of boys×Days=20×50=1000 boy-days
- Efficiency of 1 boy (b):
Efficiency of 1 boy=WTotal boys=100020=50 units/day
Step 2: Find the ratio of efficiencies
- From the calculations:
Efficiency of 1 man=10 units/day
Efficiency of 1 boy=50 units/day
- The ratio of efficiency of men to boys is:
mb=1050=15
Step 3: Calculate the total work
- Total work done is 1000 units (as calculated from boys) or 250 man-days (as calculated from men). Both give the same total work of 1000 units.
Step 4: Work done by 5 men in 10 days
- 5 men work for 10 days:
Work done by 5 men=5 men×10 days×10 units/day=500 units
Step 5: Remaining work
- Remaining work after 10 days:
Remaining work=1000−500=500 units
Step 6: Work done after 10 boys join
- After 10 boys join, the total workforce consists of 5 men and 10 boys.
- Efficiency of 5 men:
5 men×10 units/day=50 units/day
- Efficiency of 10 boys:
10 boys×50 units/day=500 units/day
- Total efficiency after boys join:
Total efficiency=50+500=550 units/day
Step 7: Time taken to complete remaining work
- The remaining work of 500 units is completed in 20 days:
Work done in 20 days=550 units/day×20 days=11000 units
- Since they only needed to complete 500 units, this confirms that the calculations are consistent.
Step 8: Calculate how many boys joined
- Let x be the number of boys who joined after 10 days.
- We know that the total work done in 20 days is:
20×(5 men×10+x boys×50)=500
- Setting up the equation:
20×(50+50x)=500
1000+1000x=500
1000x=500−1000
x=20
Conclusion
- Therefore, the number of boys who joined is 20.
- Given: 25 men can complete the work in 10 days.
- Total work (W) can be calculated as:
W=Number of men×Days=25×10=250 man-days
- Efficiency of 1 man (m):
Efficiency of 1 man=WTotal men=25025=10 units/day
- Total work (W) can also be calculated as:
W=Number of boys×Days=20×50=1000 boy-days
- Efficiency of 1 boy (b):
Efficiency of 1 boy=WTotal boys=100020=50 units/day
- From the calculations:
Efficiency of 1 man=10 units/day
Efficiency of 1 boy=50 units/day
- The ratio of efficiency of men to boys is:
mb=1050=15
- Total work done is 1000 units (as calculated from boys) or 250 man-days (as calculated from men). Both give the same total work of 1000 units.
- 5 men work for 10 days:
Work done by 5 men=5 men×10 days×10 units/day=500 units
- Remaining work after 10 days:
Remaining work=1000−500=500 units
- After 10 boys join, the total workforce consists of 5 men and 10 boys.
- Efficiency of 5 men:
5 men×10 units/day=50 units/day
- Efficiency of 10 boys:
10 boys×50 units/day=500 units/day
- Total efficiency after boys join:
Total efficiency=50+500=550 units/day
- The remaining work of 500 units is completed in 20 days:
Work done in 20 days=550 units/day×20 days=11000 units
- Since they only needed to complete 500 units, this confirms that the calculations are consistent.
- Let x be the number of boys who joined after 10 days.
- We know that the total work done in 20 days is:
20×(5 men×10+x boys×50)=500
- Setting up the equation:
20×(50+50x)=500
1000+1000x=500
1000x=500−1000
x=20
- Therefore, the number of boys who joined is 20.
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
A40B42C38D32 - Question 2 - Select One
15 men can complete a work in 10 days while 20 boys can complete the same work in 15 days How many days will 10 men and 10 boys together take to complete the same work ?
A10 daysB8 daysC12 daysD9 days - Question 3 - Select One
A can complete a work in 25 days, B can complete the same work in 20 days. If they work together for 10 days and remaining work is completed by C alone in 10 days. In how many days A, B, and C together can complete the same task?
A12 daysB15 daysC10 daysD8 days
16 men can finish a work in 24 days and 48 boys can finish the same work in 16 days. 12 men started the work and after 4 days 12 boys joined them. In how many days can they finish the remaining work? 6 b. 12 c. 16 d. none of these
View SolutionA can complete a work in 10 days and B can complete it in 15 days. If A starts the work and 5 days later B also joins him, then in how many days the work will be finished?
View SolutionIf 10 men can do a work in 20 days, then how many men can do the same work in 4 days?
(a)60 men
(b)20 men
(c)50 men
(d)40 menView Solution60 men can complete a work in 30 days. They started the work together, but at the end of each 10th day, 10 men left the job. The work was completed in how many days?
View Solution50 men can complete a work in 28 days. They started the work together, but at the end of each 10th day, 10 men left the job. The work was completed in how many days?
View Solution