Three workers A, B and C working together completed a job in 10 days. However, C only worked for the first three days when 37% of the job was done. Also, the work done by A in 5 days is equal to the work done by B in 4 days. How many days would be required by the worker C to complete the entire work?
20 days
25 days
30 days
40 days
The correct Answer is:C
Step by step video, text & image solution for Three workers A, B and C working together completed a job in 10 days. However, C only worked for the first three days when 37% of the job was done. Also, the work done by A in 5 days is equal to the work done by B in 4 days. How many days would be required by the worker C to complete the entire work? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Topper's Solved these Questions
Similar Questions
Work done by A in 3 days is equal to the work done by B in 4 days. What is the ratio of time taken by A and B to complete a work?
View SolutionA, B and C working together can finish a piece of work in 32 days. They worked for 24 days and after that the C left. Rest of the work is completed by A and B in 28 days. Work done by A in 1 day is equal to work done by B in 2 days. In how many days working alone each one will finish the work?
View Solution
Knowledge Check
- Question 1 - Select One
Three workers A, B and C working together completed a job in 10 days. However, C only worked for the first three days when 37% of the job was done. Also, the work done by A in 5 days is equal to the work done by B in 4 days. How many days would be required by the worker C to complete the entire work?
A20 daysB25 daysC30 daysD40 days - Question 2 - Select One
A and B work together to complete the rest of a job in 7 days. However, 37100 of the job was already done. Also, the work done by A in 5 days is equal to the work done by B in 4 days. How many days would be required by the fastest worker to complete the entire work?
A20B25C30D10 - Question 3 - Select One
10 men and 8 women together can complete a work in 5 days. Work done by one woman in a day is equal to half the work done by a man in 1 day. How many days will it take for 4 men and 6 women to complete that work?
A12 daysB10 daysC8 daysD4 days
A, B and C working together can finish certain piece of work in 28 days. They work together for 18 days, then B left. If rest work done by A and C in 25 days. Work done by A in 2 days is equal to work done by C in 3 days, then find in how many days A, B and C working alone will finish the work?
View SolutionTwo workers 'A' and 'B' working together completed a job in 5 days. Had 'A' worked twice as efficiently as he actually did, the work would have completed in 3 days. In how many days could 'A' alone complete the job ?
View SolutionA can do a job in 12 days and B can do the same job in 6 days, in how many days working together they can complete the job?
View Solution10 men and 8 women can together complete a work in 5 days. Work done by a woman is equal to the half of the work done by a man. In how many days, will 4 men and 6 women complete that work ?
View SolutionTwo workers A and B working together completed a job in 5 days. If A worked twice as efficiently as he actually did and B worked 13 as efficiently as he actually did, the work would have been completed in 3 days. To complete the job alone. A would require
View Solution