A can do a certain job in 15 days. B is 50% more efficient than A. Then B can do the same piece of work in
15
10
12
17
The correct Answer is:D
To solve the problem step by step, we will determine how long it takes for B to complete the same job that A can do in 15 days, given that B is 50% more efficient than A.
1. Determine A's Efficiency:
- A can complete the job in 15 days.
- If we consider A's efficiency as 100 units of work per day, then in 15 days, A completes:
Total Work=Efficiency of A×Time taken by A=100×15=1500 units of work
2. Calculate B's Efficiency:
- B is 50% more efficient than A.
- Therefore, B's efficiency can be calculated as:
Efficiency of B=Efficiency of A+50% of Efficiency of A=100+50=150 units of work per day
3. Calculate Time Taken by B:
- Since both A and B are doing the same amount of work (1500 units), we can set up the equation:
Total Work=Efficiency of B×Time taken by B
- Substituting the known values:
1500=150×Time taken by B
- To find the time taken by B, we rearrange the equation:
Time taken by B=1500150=10 days
4. Conclusion:
- Therefore, B can complete the same piece of work in 10 days.
Final Answer:
B can do the same piece of work in 10 days.
---
- A can complete the job in 15 days.
- If we consider A's efficiency as 100 units of work per day, then in 15 days, A completes:
Total Work=Efficiency of A×Time taken by A=100×15=1500 units of work
- B is 50% more efficient than A.
- Therefore, B's efficiency can be calculated as:
Efficiency of B=Efficiency of A+50% of Efficiency of A=100+50=150 units of work per day
- Since both A and B are doing the same amount of work (1500 units), we can set up the equation:
Total Work=Efficiency of B×Time taken by B
- Substituting the known values:
1500=150×Time taken by B
- To find the time taken by B, we rearrange the equation:
Time taken by B=1500150=10 days
- Therefore, B can complete the same piece of work in 10 days.
B can do the same piece of work in 10 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
A can do a certain job in 12 days. B is 60% more efficient than A. Then B can do the same piece of work in
A8 daysB712 daysC614 daysD6 days - Question 2 - Select One
A can do a certain job in 12 days. B is 60% more efficient than A. To do the same job B alone would take?
A712 daysB8 daysC10 daysD7 days - Question 3 - Select One
A can do a piece of work in 15 days. B is 50% more efficient than A, B can finish it in
A10daysB712 daysC12daysD1012 days
A can do a certain job in 12 days. B in 60% more efficient than A. What is the number of days it takes B to do the same piece of work ?
View SolutionA can do a piece of work in 24 days. If B is 60% more efficient than A, then how many days does B require to do the same work?
View SolutionA can do a certain job in 12 days. B in 60% more efficient than A. What is the number of days it takes B to do the same piece of work ?
View SolutionA can do a picec of work in 10 days and B is 25% more
efficient than A. In what time will the work be finished if A
and B work together ?View SolutionPeter can do a piece of work in 12 days. Mohan is 50% more efficient than Pter. If Mohan is given that piece of work, how long will he take to do it?
View Solution