Doubtnut Promotions Sticky

A can do a certain job in 15 days. B is 50% more efficient than A. Then B can do the same piece of work in

A

15

B

10

C

12

D

17

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we will determine how long it takes for B to complete the same job that A can do in 15 days, given that B is 50% more efficient than A.

1. Determine A's Efficiency:
- A can complete the job in 15 days.
- If we consider A's efficiency as 100 units of work per day, then in 15 days, A completes:
Total Work=Efficiency of A×Time taken by A=100×15=1500 units of work

2. Calculate B's Efficiency:
- B is 50% more efficient than A.
- Therefore, B's efficiency can be calculated as:
Efficiency of B=Efficiency of A+50% of Efficiency of A=100+50=150 units of work per day

3. Calculate Time Taken by B:
- Since both A and B are doing the same amount of work (1500 units), we can set up the equation:
Total Work=Efficiency of B×Time taken by B
- Substituting the known values:
1500=150×Time taken by B
- To find the time taken by B, we rearrange the equation:
Time taken by B=1500150=10 days

4. Conclusion:
- Therefore, B can complete the same piece of work in 10 days.

Final Answer:
B can do the same piece of work in 10 days.

---

|
Updated on:18/9/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do a certain job in 12 days. B is 60% more efficient than A. Then B can do the same piece of work in

    A8 days
    B712 days
    C614 days
    D6 days
  • Question 2 - Select One

    A can do a certain job in 12 days. B is 60% more efficient than A. To do the same job B alone would take?

    A712 days
    B8 days
    C10 days
    D7 days
  • Question 3 - Select One

    A can do a piece of work in 15 days. B is 50% more efficient than A, B can finish it in

    A10days
    B712 days
    C12days
    D1012 days