Doubtnut Promotions Sticky

150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.

Video Solution
Text Solution
Verified by Experts

The correct Answer is:N/a


Let the work is completed in 'n' days.
No. of workers engaged on second day =150-4=146
No. of workers engaged of third day =1502×4=142
Series formed from n terms : 150, 146, 142,….
Hera a=150,d=146150=142146=4
Sn=n2[2a+(n1)d]
=n2[2×150+(n1)(4)]=152n2n2
If 150 workers engaged then work completes in (n-8) days
150(n8)=1522n2
2n22n1200=0
n2n600=0
(n25)(n+24)=0
n25=0orn+24=0
n=25or n=24
n=24 is not possible.
Therefore, work is completed in 25 days.

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions