Doubtnut Promotions Sticky

35 persons are engaged to complete a work in 60 days. After 32 days it is observed that only (2/5)th part of the work has been done. The number of persons to be engaged to complete the remaining work in the said period is

A

20

B

35

C

30

D

25

Video Solution
Doubtnut Promotions Banner
|
Answer

Step by step video & image solution for 35 persons are engaged to complete a work in 60 days. After 32 days it is observed that only (2/5)th part of the work has been done. The number of persons to be engaged to complete the remaining work in the said period is by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Related Playlists


Knowledge Check

  • Question 1 - Select One

    14 persons can complete a work in 16 days. 8 persons started the work 12 days after they started the work 8 more persons joined them. How many days will they take to complete the remaining work ?

    A12 days
    B7 days
    C9 days
    DNone of these
  • Question 1 - Select One

    A contractor undertook a work to complete in 60 days. But just after 20 days he observed that only 15th of the project work had been completed. To complete the work in time in rest days minimum how many workers he had to increase, if there were initially 75 workers were deployed for the task?

    A25
    B50
    C75
    Dcan't be determined
  • Question 1 - Select One

    25 persons complete a work in 50 days. In how many days will 10 persons complete the work ?

    A120
    B125
    C100
    D215
  • Question 1 - Select One

    A can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be

    A6 days
    B8 days
    C9 days
    D5 days
  • Question 1 - Select One

    If 40 persons can do a piece of work in 14 days, then the number of persons required to complete the work in 28 days.

    A40
    B20
    C14
    D10
  • Question 1 - Select One

    If 20 persons can do a piece of work in 7 days, then the number of persons required to complete the work in 28 days:

    A4
    B5
    C14
    D10
  • Question 1 - Select One

    24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :

    A32 men
    B30 men
    C35 men
    D36 men

Similar Questions