A is twice as good a workman as B and C is thrice as good a workman as B and C is thrice as good a workman as B . If A, B and C together can complete a work in 2 days , then in how many days can A alone complete the work ?
The correct Answer is:6
To solve the problem step by step, we can follow these instructions:
Step 1: Define the efficiencies of A, B, and C
Let the efficiency of workman B be represented as K. According to the problem:
- A is twice as good as B, so A=2K.
- C is thrice as good as B, so C=3K.
Step 2: Calculate the combined efficiency of A, B, and C
Now, we can find the total efficiency when A, B, and C work together:
Total Efficiency=A+B+C=2K+K+3K=6K
Step 3: Determine the amount of work done in a day
According to the problem, A, B, and C together can complete the work in 2 days. This means that in one day, they complete half of the work. Therefore, the work done in one day is:
Work done in 1 day=12 (of the total work)
Step 4: Set up the equation for total work
Since the total work done in one day is equal to their combined efficiency, we can set up the equation:
6K=12
Step 5: Solve for K
To find K, we multiply both sides by 2:
12K=1⟹K=112
Step 6: Find A's efficiency
Now that we have K, we can find A's efficiency:
A=2K=2×112=16
Step 7: Calculate the time taken by A to complete the work alone
If A's efficiency is 16, it means A can complete 16 of the work in one day. Therefore, the time taken by A to complete the entire work is:
Time taken by A=116=6 days
Final Answer
A alone can complete the work in 6 days.
---
Let the efficiency of workman B be represented as K. According to the problem:
- A is twice as good as B, so A=2K.
- C is thrice as good as B, so C=3K.
Now, we can find the total efficiency when A, B, and C work together:
Total Efficiency=A+B+C=2K+K+3K=6K
According to the problem, A, B, and C together can complete the work in 2 days. This means that in one day, they complete half of the work. Therefore, the work done in one day is:
Work done in 1 day=12 (of the total work)
Since the total work done in one day is equal to their combined efficiency, we can set up the equation:
6K=12
To find K, we multiply both sides by 2:
12K=1⟹K=112
Now that we have K, we can find A's efficiency:
A=2K=2×112=16
If A's efficiency is 16, it means A can complete 16 of the work in one day. Therefore, the time taken by A to complete the entire work is:
Time taken by A=116=6 days
A alone can complete the work in 6 days.
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - MOCK TEST PAPEREXERCISE - Questions5videos
MOCK TEST PAPER
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - MENSURATIONEXERCISE - Concept Application (Level 3 )8videos
MENSURATION
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - PERCENTAGESEXERCISE - Concept Application (LEVEL 3)7videos
PERCENTAGES
Similar Questions
Knowledge Check
- Question 1 - Select One
A is twice as good a workman as B and B is twice as good a workman as C. If A and B can together finish a piece of work in 4 days, then C can do it by himself in
A6 daysB8 daysC24 daysD12 days - Question 2 - Select One
If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many day can A alone complete the work?
A60 daysB45 daysC40 daysD30 days - Question 3 - Select One
A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
A4B15C154D16
A is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?
View SolutionA works thrice as much as B. If A can complete this work in 12 days, then in how many days will both A and B complete this work ?
View SolutionA is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can A alone finish the work?
View SolutionA is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can B alone finish the work?
View SolutionA is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can A alone finish the work?
View Solution