A and C started doing a work . After working for 6 days , both left and B alone completed the remaining work in 4 days .In how many days can C alone complete a work in 2 days , then in how many days can A alone complete the work ?
Text Solution
The correct Answer is:18
|
Updated on:21/07/2023
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - MOCK TEST PAPEREXERCISE - Questions5videos
MOCK TEST PAPER
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - MENSURATIONEXERCISE - Concept Application (Level 3 )8videos
MENSURATION
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - PERCENTAGESEXERCISE - Concept Application (LEVEL 3)7videos
PERCENTAGES
Similar Questions
Knowledge Check
- Question 1 - Select One
A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?
A38B51C46D62 - Question 2 - Select One
A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
A4B15C154D16 - Question 3 - Select One
A alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?
A6 daysB4 daysC10 daysD8 days
A is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?
View SolutionA and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?
View SolutionP and Q together can complete a work in 20 days. If P alone can complete the same work in 36 days, then in how many days Q alone can complete the same work?
View SolutionIf Rohit alone can complete one-fourth of a work in 32 days, then in how many days Rohit alone can complete the whole work?
View SolutionIf C alone can complete two-third part of a work in 12 days, then in how many days C can complete the whole work?
View Solution