Doubtnut Promotions Sticky

A is thrice as productive as C. Together they can complete a job in 22.5 days. If B joins them after they have worked for 15 days then in how many days can they finish the rest of the job if B alone can do the job in 15 days?

A

6

B

3

C

9

D

2

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will first determine the efficiencies of A, B, and C, and then calculate how much work they can complete together.

Step 1: Determine the efficiencies of A, B, and C
Given that A is thrice as productive as C, we can denote the efficiency of C as x. Therefore, the efficiency of A will be 3x.

Now, the combined efficiency of A and C is:
Efficiency of A and C=A+C=3x+x=4x

We know that A and C can complete the job in 22.5 days. Thus, their combined work rate (efficiency) can be calculated as:
Total work=Efficiency×Time
Let’s denote the total work as W. Therefore:
W=4x×22.5

Step 2: Calculate the total work (W)
To find W, we can express it in terms of x:
W=4x×22.5=90x

Step 3: Determine the efficiency of B
B can complete the job alone in 15 days. Thus, B's efficiency is:
Efficiency of B=W15=90x15=6x

Step 4: Calculate the work done by A and C in 15 days
Now, we need to find out how much work A and C can complete in 15 days:
Work done by A and C in 15 days=Efficiency of A and C×Time=4x×15=60x

Step 5: Calculate the remaining work
Now, we can find the remaining work after A and C have worked for 15 days:
Remaining work=WWork done by A and C=90x60x=30x

Step 6: Calculate the combined efficiency of A, B, and C
When B joins A and C, their combined efficiency becomes:
Combined efficiency of A, B, and C=4x+6x=10x

Step 7: Calculate the time taken to finish the remaining work
Now, we need to find out how many days it will take for A, B, and C to finish the remaining work of 30x:
Time=Remaining workCombined efficiency=30x10x=3 days

Conclusion
Thus, A, B, and C can finish the remaining work in 3 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If A alone can do a job in 40 days then, in how many days can B alone do the job if together they can do the job in 8 days?

    A15
    B10
    C20
    D25
  • Question 2 - Select One

    A,B and C together can finish a job in 4 days .A and B together can finish the same job in 5 days .In how many days ,C alone will finish the same job ?

    A12
    B16
    C20
    D24
  • Question 3 - Select One

    A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3 : 2. In how many days can the faster person complete the job?

    A50
    B30
    C40
    D60