6 Men+10 women can reep 5/12 part of 360 hectare land in 15 days by working 6 Hrs per day. If now 2 more men and 4 women are employed. then the work will be finished in how many days by working 7 Hrs per day. it is also given that work ratio of 2 man = 3 women?
a)13.25
b)13.25
c)14.25
d)14.15
The correct Answer is:B
To solve the problem step by step, we will follow the given information and perform the necessary calculations.
Step 1: Calculate the total work done
Given that 6 men and 10 women can reap 512 of 360 hectares in 15 days by working 6 hours per day.
First, we calculate the total area of land:
Total area=360 hectares
Now, calculate the area reaped:
Area reaped=512×360=150 hectares
Next, we calculate the total work done in terms of man-hours:
Total man-hours=Number of days×Hours per day=15×6=90 hours
Step 2: Calculate the efficiency of 6 men and 10 women
Let’s denote the work done by 1 man in 1 hour as M and the work done by 1 woman in 1 hour as W.
From the problem, we know that:
6M+10W can complete 150 hectares in 90 hours.
Thus, the total work done in man-hours is:
(6M+10W)×90=150
6M+10W=15090=53
Step 3: Convert men to women using the given ratio
We are given the ratio 2M=3W, which implies:
M=1.5W
Substituting M in the equation:
6(1.5W)+10W=53
9W+10W=53
19W=53
W=557
Now substituting back to find M:
M=1.5W=1.5×557=7.557=538
Step 4: Calculate the remaining work
The total work in terms of units is:
Total work=360 hectares=360 units
The work already done is:
Work done=150 hectares=150 units
Remaining work:
Remaining work=360−150=210 units
Step 5: Calculate the new workforce
Now, 2 more men and 4 more women are employed:
New number of men=6+2=8
New number of women=10+4=14
Convert men to women:
8M=8×1.5W=12W
Total workforce in terms of women:
Total women=12W+14W=26W
Step 6: Calculate the time to finish the remaining work
Now, they will work for 7 hours a day. The total work done in one day is:
Daily work=26W×7 hours=182 units
To find the number of days required to finish the remaining work:
Days required=Remaining workDaily work=210182≈1.15 days
Final Answer
Thus, the work will be finished in approximately 1.15 days.
Given that 6 men and 10 women can reap 512 of 360 hectares in 15 days by working 6 hours per day.
Total area=360 hectares
Area reaped=512×360=150 hectares
Total man-hours=Number of days×Hours per day=15×6=90 hours
Let’s denote the work done by 1 man in 1 hour as M and the work done by 1 woman in 1 hour as W.
6M+10W can complete 150 hectares in 90 hours.
(6M+10W)×90=150
6M+10W=15090=53
We are given the ratio 2M=3W, which implies:
M=1.5W
6(1.5W)+10W=53
9W+10W=53
19W=53
W=557
M=1.5W=1.5×557=7.557=538
The total work in terms of units is:
Total work=360 hectares=360 units
Work done=150 hectares=150 units
Remaining work=360−150=210 units
Now, 2 more men and 4 more women are employed:
New number of men=6+2=8
New number of women=10+4=14
8M=8×1.5W=12W
Total women=12W+14W=26W
Now, they will work for 7 hours a day. The total work done in one day is:
Daily work=26W×7 hours=182 units
Days required=Remaining workDaily work=210182≈1.15 days
Thus, the work will be finished in approximately 1.15 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
5 men can do a work in 6 days and 10 women can do the same work in 5 days. In how many days the work is done by 5 women and 3 men?
A10 daysB8 daysC6 daysD5 days - Question 2 - Select One or More
3 men or 5 women can do a work in 12 days. How long will 6 men and 5 women take to finish the work?
A4 daysB5 daysC6 daysD7 days - Question 3 - Select One
2 men and 3 women finish 25% of the work in 4 days, while 6 men and 14 women can finish the whole work in 5 days. In how many days will 20 women finish it?
A20B25C24D88
38 men can complete a work by working 6 Hrs per day in 12 days then calculate in how many days 51 men can do double of the work by work ing 8 hrs per day?
View Solution3 men can do a piece of work in 6 days. 5 women can do the same work in 18 days. If 4 men and 10 women work together, then how long will it take to finish the work?
View Solution12 men can complete a work in 16 days and 16 women can complete the same work in 12 days In how many days will 4 men and 8 women complete that work ?
View SolutionIf 10 men working for 6 hours per day can complete a piece of work in 90 days, in how many days will 6 men working for 15 hours per day complete the same piece of work ?
View SolutionIt is given that men are twice as efficient than women in respect to doing work. If three men and two women can complete the work in 2 days, then in how many days can a woman working alone complete the work?
यह दिया गया है कि किसी कार्य को करने में पुरुष महिलाओं से दोगुने कार्य कुशल हैं | यदि तीन पुरुष और दो महिलाओं को किसी कार्य को समाप्त करने में 2 दिन लगते हैं, तो एक महिला अकेले कार्य करते हुए इस कार्य को कितने दिनों में समाप्त कर सकती है?View Solution