Doubtnut Promotions Sticky

6 Men+10 women can reep 5/12 part of 360 hectare land in 15 days by working 6 Hrs per day. If now 2 more men and 4 women are employed. then the work will be finished in how many days by working 7 Hrs per day. it is also given that work ratio of 2 man = 3 women?

A

a)13.25

B

b)13.25

C

c)14.25

D

d)14.15

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will follow the given information and perform the necessary calculations.

Step 1: Calculate the total work done
Given that 6 men and 10 women can reap 512 of 360 hectares in 15 days by working 6 hours per day.

First, we calculate the total area of land:
Total area=360 hectares

Now, calculate the area reaped:
Area reaped=512×360=150 hectares

Next, we calculate the total work done in terms of man-hours:
Total man-hours=Number of days×Hours per day=15×6=90 hours

Step 2: Calculate the efficiency of 6 men and 10 women
Let’s denote the work done by 1 man in 1 hour as M and the work done by 1 woman in 1 hour as W.

From the problem, we know that:
6M+10W can complete 150 hectares in 90 hours.

Thus, the total work done in man-hours is:
(6M+10W)×90=150
6M+10W=15090=53

Step 3: Convert men to women using the given ratio
We are given the ratio 2M=3W, which implies:
M=1.5W

Substituting M in the equation:
6(1.5W)+10W=53
9W+10W=53
19W=53
W=557

Now substituting back to find M:
M=1.5W=1.5×557=7.557=538

Step 4: Calculate the remaining work
The total work in terms of units is:
Total work=360 hectares=360 units

The work already done is:
Work done=150 hectares=150 units

Remaining work:
Remaining work=360150=210 units

Step 5: Calculate the new workforce
Now, 2 more men and 4 more women are employed:
New number of men=6+2=8
New number of women=10+4=14

Convert men to women:
8M=8×1.5W=12W

Total workforce in terms of women:
Total women=12W+14W=26W

Step 6: Calculate the time to finish the remaining work
Now, they will work for 7 hours a day. The total work done in one day is:
Daily work=26W×7 hours=182 units

To find the number of days required to finish the remaining work:
Days required=Remaining workDaily work=2101821.15 days

Final Answer
Thus, the work will be finished in approximately 1.15 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    5 men can do a work in 6 days and 10 women can do the same work in 5 days. In how many days the work is done by 5 women and 3 men?

    A10 days
    B8 days
    C6 days
    D5 days
  • Question 2 - Select One or More

    3 men or 5 women can do a work in 12 days. How long will 6 men and 5 women take to finish the work?

    A4 days
    B5 days
    C6 days
    D7 days
  • Question 3 - Select One

    2 men and 3 women finish 25% of the work in 4 days, while 6 men and 14 women can finish the whole work in 5 days. In how many days will 20 women finish it?

    A20
    B25
    C24
    D88