16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?
4 days
6 days
8 days
10 days
The correct Answer is:B
Step by step video, text & image solution for 16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Related Playlists
Similar Questions
16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?
View SolutionA piec of work can be done by 12 men in 24 days. They started the work and after 4 days then 6 more men joined them. How many days will they all take to complete the remaining work ?
View Solution45 men can complete a work in 16 days. Four days after they started working, 36 more men joined them. How many days will they now take to complete the remaining work?
View Solution18 men can complete a work in 9 days. After they have worked for 5 days, 6 more men join them. How many days will they take to complete the remaining work ?
18 पुरुष किसी कार्य को 9 दिनों में पूरा कर सकते हैं | उनके 5 दिनों तक कार्य कर लेने के बाद, 6 अतिरिक्त पुरुष उनके साथ हो गए | शेष कार्य करने में उन्हें कितना समय लगेगा ?View Solution45 men can complete a work in 16 days. Six days after they started working, 30 more men joined them. How many days will they now take to complete the remaining work?
View SolutionThree men can complete a plece of work in 6 days. Two days after they started the work, 3 more men joined them. How many days will they take to complete the remaining work?
View Solution12 men complete a work in 18 days. Six days after they had started working, 4 men joined them. How many days will all of them take to complete the remaining work ?
View Solution14 persons can complete a work in 16 days. 8 persons started the work 12 days after they started the work 8 more persons joined them. How many days will they take to complete the remaining work ?
View Solution14 men can complete a work in 12 days. 4 days after they started the work, 2 more men joined them. How many days will they take to complete the remaining work ?
View Solution12 men can complete a work within 9 days. After 3 days they started the work, 6 men joined them to replace 2 men. How many days will they take to complete the remaining work?
View Solution