Doubtnut Promotions Sticky

18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 6 hours a day?

A

25

B

15

C

20

D

9

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will use the concept of work done, which can be calculated using the formula:

Work=Number of Persons×Hours per Day×Days

Step 1: Calculate the total work done in the first scenario
Given:
- Number of persons (M1) = 18
- Hours per day (H1) = 8
- Days (D1) = 10
- Units of work (W1) = 3

Using the formula, we can calculate the total work done in terms of person-hours:
Total Work=M1×H1×D1=18×8×10=1440 person-hours

Step 2: Calculate the work done per unit
Since 3 units of work are completed in 1440 person-hours, the work done per unit can be calculated as:
Work per unit=Total WorkUnits of Work=14403=480 person-hours per unit

Step 3: Calculate the total work required for the second scenario
Now, we need to find out how much work is required for 5 units of work:
Total Work Required=5×Work per unit=5×480=2400 person-hours

Step 4: Set up the equation for the second scenario
Now we need to find out how many persons (M2) are required to complete this work in the second scenario:
- Hours per day (H2) = 6
- Days (D2) = 16

Using the formula for work, we have:
Total Work Required=M2×H2×D2
Substituting the known values:
2400=M2×6×16

Step 5: Solve for M2
Now, we can solve for M2:
2400=M2×96
M2=240096=25

Conclusion
Thus, the number of persons required to complete 5 units of work in 16 days working 6 hours a day is 25.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    24 persons working 8 hours a day can complete 2 units of a work in 10 days. How many persons are required to complete 4 units of that work, if they work 6 hours a day for 16 days?
    एक दिन में 8 घंटे कार्य करते हुए 24 व्यक्ति किसी कार्य की 2 इकाई 10 दिनों में समाप्त कर सकते हैं | इस कार्य की 4 इकाई समाप्त करने के लिए कितने लोगों की आवश्यकता होगी यदि वे 16 दिनों तक एक दिन में 6 घंटे कार्य करते हैं ?

    A48
    B36
    C40
    D32
  • Question 2 - Select One

    36 persons working 8 hours a day can do 3 units of work in 12 days. How many persons are required to do 5 units of that work in 16 days, if they work for 6 hours a day?

    A50
    B55
    C60
    D45
  • Question 3 - Select One

    36 persons working 8 hours a day can do 3 units of work in 12 days. How many persons are required to do 5 units of that work in 16 days, if they work for 6 hours a day?
    प्रतिदिन 8 घंटे कार्य करके 36 लोग किसी कार्य की 3 इकाई 12 दिनों में कर सकते हैं| यदि वे एक दिन में 6 घंटे कार्य करें तो 16 दिन में इस कार्य की 5 इकाई समाप्त करने के लिए कितने लोगों की आवश्यकता होगी ?

    A50
    B55
    C60
    D45