Working 5 hours a day. A can complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in
3 days
4 days
4.5 days
5.4 days
The correct Answer is:A
To solve the problem step by step, we need to determine how long A and B will take to complete the work when they work together for 8 hours a day.
Step 1: Calculate the total work done by A and B
1. Calculate A's work rate:
- A can complete the work in 8 days, working 5 hours a day.
- Total hours A works = 8 days × 5 hours/day = 40 hours.
- Therefore, A's work rate = Total work / Total hours = 1 work unit / 40 hours = 1/40 work units per hour.
2. Calculate B's work rate:
- B can complete the work in 10 days, working 6 hours a day.
- Total hours B works = 10 days × 6 hours/day = 60 hours.
- Therefore, B's work rate = Total work / Total hours = 1 work unit / 60 hours = 1/60 work units per hour.
Step 2: Combine the work rates of A and B
3. Calculate their combined work rate:
- Combined work rate = A's work rate + B's work rate
- Combined work rate = (1/40 + 1/60) work units per hour.
4. Finding a common denominator:
- The least common multiple (LCM) of 40 and 60 is 120.
- Convert the fractions:
- (1/40) = (3/120)
- (1/60) = (2/120)
- Therefore, combined work rate = (3/120 + 2/120) = (5/120) = (1/24) work units per hour.
Step 3: Calculate the time taken to complete the work together
5. Calculate the time taken to complete the work together:
- If A and B work together, they complete 1/24 of the work in 1 hour.
- To complete 1 work unit, the time taken = 1 work unit / (1/24 work units per hour) = 24 hours.
Step 4: Calculate how many days they will take working 8 hours a day
6. Calculate the number of days required:
- If they work 8 hours a day, the number of days required = Total hours / Hours per day = 24 hours / 8 hours/day = 3 days.
Final Answer:
A and B can jointly complete the work in 3 days when working 8 hours a day.
---
- A can complete the work in 8 days, working 5 hours a day.
- Total hours A works = 8 days × 5 hours/day = 40 hours.
- Therefore, A's work rate = Total work / Total hours = 1 work unit / 40 hours = 1/40 work units per hour.
- B can complete the work in 10 days, working 6 hours a day.
- Total hours B works = 10 days × 6 hours/day = 60 hours.
- Therefore, B's work rate = Total work / Total hours = 1 work unit / 60 hours = 1/60 work units per hour.
- Combined work rate = A's work rate + B's work rate
- Combined work rate = (1/40 + 1/60) work units per hour.
- The least common multiple (LCM) of 40 and 60 is 120.
- Convert the fractions:
- (1/40) = (3/120)
- (1/60) = (2/120)
- Therefore, combined work rate = (3/120 + 2/120) = (5/120) = (1/24) work units per hour.
- If A and B work together, they complete 1/24 of the work in 1 hour.
- To complete 1 work unit, the time taken = 1 work unit / (1/24 work units per hour) = 24 hours.
- If they work 8 hours a day, the number of days required = Total hours / Hours per day = 24 hours / 8 hours/day = 3 days.
A and B can jointly complete the work in 3 days when working 8 hours a day.
Topper's Solved these Questions
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TEST YOURSELF25videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-V19videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND DISTANCEEXERCISE - Type -XI74videos
TIME AND DISTANCE
- BOOK - KIRAN PUBLICATIONCHAPTER - TRIGONOMETRY EXERCISE - TEST YOURSELF25videos
TRIGONOMETRY
Similar Questions
P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work ? 5511 b. 5611 c. 6611 d. 6611
View Solution10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days.
View Solution
Knowledge Check
- Question 1 - Select One
Working 2 hours in a day, P can complete a work in 10 days and working 5 hours in a day, Q can complete the same work in 6 days. Working 3 hours in a day, in how many days both P and Q together can complete the same work?
A3 daysB6 daysC4 daysD5 days - Question 2 - Select One
If 40 men working 12 hours a day can complete a work in 8 days, then how many men working 4 hours a day can complete the same work in 16 days ?
यदि 40 लोग प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 8 दिनों में समाप्त कर सकते हैं, तो इस कार्य को प्रतिदिन 4 घंटे कार्य करते हुए 16 दिनों में समाप्त करने के लिए कितने पुरुषों की आवश्यकता होगी ?A50B60C54D45 - Question 3 - Select One
P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how man days can they complete the work ?
A5511B5611C6511D6611
Uday working 4 hours a day completes a work in 10 days, while Subhash working 8 hours a day can complete the same work in 15 days. How many days will it take for both of them working together 10 hours a day to complete the work ?
View Solution10 men, working. 6 hours a day can compJete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days?
View SolutionP can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work ? 5511 b. 5611 c. 6611 d. 6611
View SolutionA person invests money in two different schemes for 5 years and 8 years at 12% and 10% simple interest, respectively. At the completion of each scheme he gets the same interest. The ratio of his investments is
View SolutionA man working 8 hours a day takes 5 days to complete a project. How many hours a day must he work to complete. It in 4 days?
View Solution