Doubtnut Promotions Sticky

A road of 5 km length will be con structed in 100 days. So 280 workers were employed. But after 80 days it was found that only 312 km road was completed. Now how many more people were needed to finish the work in the specified time?

A

480

B

80

C

200

D

100

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will break down the information given and calculate how many more workers are needed to complete the road construction on time.

Step 1: Understand the problem
- A road of length 5 km is to be constructed in 100 days.
- 280 workers are employed for this task.
- After 80 days, only 3.5 km of the road has been completed.

Step 2: Calculate the amount of work completed
- Total work required = 5 km
- Work completed in 80 days = 3.5 km
- Work remaining = Total work - Work completed = 5 km - 3.5 km = 1.5 km

Step 3: Determine the remaining time
- Total time for construction = 100 days
- Time spent = 80 days
- Remaining time = Total time - Time spent = 100 days - 80 days = 20 days

Step 4: Calculate the work done per day by the current workers
- Work done by 280 workers in 80 days = 3.5 km
- Work done per day = Total work done / Number of days = 3.5 km / 80 days = 0.04375 km/day

Step 5: Calculate the total work rate needed to finish the remaining work
- Remaining work = 1.5 km
- Time left = 20 days
- Required work rate to finish on time = Remaining work / Remaining time = 1.5 km / 20 days = 0.075 km/day

Step 6: Calculate the number of workers needed to achieve the required work rate
- Current work rate of 280 workers = 0.04375 km/day
- Work rate per worker = 0.04375 km/day / 280 workers = 0.00015625 km/worker/day
- Required number of workers = Required work rate / Work rate per worker = 0.075 km/day / 0.00015625 km/worker/day

Step 7: Calculate the required number of workers
- Required number of workers = 0.075 / 0.00015625 = 480 workers

Step 8: Calculate how many more workers are needed
- Current number of workers = 280
- Additional workers needed = Required workers - Current workers = 480 - 280 = 200 workers

Final Answer
200 more workers are needed to finish the work in the specified time.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    36 workmen are employed to finish a certain work in 48 days. But it is found that in 24 days only 2/5 work is done. How many more men must be employed to finish the work in time?

    A16
    B18
    C20
    D22
  • Question 2 - Select One

    90 men are engaged to do a piece of work in 40 days but it is found that in 25 days, 2/3 work is completed. How many men should be allowed to go off, so that the work may be finished in time?

    A10
    B15
    C20
    D25
  • Question 3 - Select One

    A contractor undertakes to make a mall in 60 days and he
    employs 30 men. After 30 days it is found that only one-
    third of the work is completed. How many extre men should
    he employ so that the work is completed on time?

    A20 men
    B25 men
    C30 men
    D40 men