A road of 5 km length will be con structed in 100 days. So 280 workers were employed. But after 80 days it was found that only 312 km road was completed. Now how many more people were needed to finish the work in the specified time?
480
80
200
100
The correct Answer is:C
To solve the problem step by step, we will break down the information given and calculate how many more workers are needed to complete the road construction on time.
Step 1: Understand the problem
- A road of length 5 km is to be constructed in 100 days.
- 280 workers are employed for this task.
- After 80 days, only 3.5 km of the road has been completed.
Step 2: Calculate the amount of work completed
- Total work required = 5 km
- Work completed in 80 days = 3.5 km
- Work remaining = Total work - Work completed = 5 km - 3.5 km = 1.5 km
Step 3: Determine the remaining time
- Total time for construction = 100 days
- Time spent = 80 days
- Remaining time = Total time - Time spent = 100 days - 80 days = 20 days
Step 4: Calculate the work done per day by the current workers
- Work done by 280 workers in 80 days = 3.5 km
- Work done per day = Total work done / Number of days = 3.5 km / 80 days = 0.04375 km/day
Step 5: Calculate the total work rate needed to finish the remaining work
- Remaining work = 1.5 km
- Time left = 20 days
- Required work rate to finish on time = Remaining work / Remaining time = 1.5 km / 20 days = 0.075 km/day
Step 6: Calculate the number of workers needed to achieve the required work rate
- Current work rate of 280 workers = 0.04375 km/day
- Work rate per worker = 0.04375 km/day / 280 workers = 0.00015625 km/worker/day
- Required number of workers = Required work rate / Work rate per worker = 0.075 km/day / 0.00015625 km/worker/day
Step 7: Calculate the required number of workers
- Required number of workers = 0.075 / 0.00015625 = 480 workers
Step 8: Calculate how many more workers are needed
- Current number of workers = 280
- Additional workers needed = Required workers - Current workers = 480 - 280 = 200 workers
Final Answer
200 more workers are needed to finish the work in the specified time.
---
- A road of length 5 km is to be constructed in 100 days.
- 280 workers are employed for this task.
- After 80 days, only 3.5 km of the road has been completed.
- Total work required = 5 km
- Work completed in 80 days = 3.5 km
- Work remaining = Total work - Work completed = 5 km - 3.5 km = 1.5 km
- Total time for construction = 100 days
- Time spent = 80 days
- Remaining time = Total time - Time spent = 100 days - 80 days = 20 days
- Work done by 280 workers in 80 days = 3.5 km
- Work done per day = Total work done / Number of days = 3.5 km / 80 days = 0.04375 km/day
- Remaining work = 1.5 km
- Time left = 20 days
- Required work rate to finish on time = Remaining work / Remaining time = 1.5 km / 20 days = 0.075 km/day
- Current work rate of 280 workers = 0.04375 km/day
- Work rate per worker = 0.04375 km/day / 280 workers = 0.00015625 km/worker/day
- Required number of workers = Required work rate / Work rate per worker = 0.075 km/day / 0.00015625 km/worker/day
- Required number of workers = 0.075 / 0.00015625 = 480 workers
- Current number of workers = 280
- Additional workers needed = Required workers - Current workers = 480 - 280 = 200 workers
200 more workers are needed to finish the work in the specified time.
Topper's Solved these Questions
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TEST YOURSELF25videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-V19videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND DISTANCEEXERCISE - Type -XI74videos
TIME AND DISTANCE
- BOOK - KIRAN PUBLICATIONCHAPTER - TRIGONOMETRY EXERCISE - TEST YOURSELF25videos
TRIGONOMETRY
Similar Questions
A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the work is completed How many men should be increased so that the work will be completed in 25 days less than the scheduled time
View SolutionA contractor undertakes to built a walls in 50 days. He employs 50 peoples for the same. However after 25 days he finds that only 40% of the work is complete. How many more man need to be employed to complete the work in time?
View Solution
Knowledge Check
- Question 1 - Select One
36 workmen are employed to finish a certain work in 48 days. But it is found that in 24 days only 2/5 work is done. How many more men must be employed to finish the work in time?
A16B18C20D22 - Question 2 - Select One
90 men are engaged to do a piece of work in 40 days but it is found that in 25 days, 2/3 work is completed. How many men should be allowed to go off, so that the work may be finished in time?
A10B15C20D25 - Question 3 - Select One
A contractor undertakes to make a mall in 60 days and he
employs 30 men. After 30 days it is found that only one-
third of the work is completed. How many extre men should
he employ so that the work is completed on time?A20 menB25 menC30 menD40 men
A contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?
View Solution20 persons completed 13rd of the work in 12 days. How many more person are required to finish rest work in next 12 days?
View Solution20 persons completed 13rd of the work in 24 days. How many more person are required to finish the rest of the work in next 12 days?
View SolutionA contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 13rd of the work was still to be done. How many more men were required to complete the work in stipulated time?
View SolutionA contractor wants to complete a project in 90 days and he employed 60 workmen. After 60 days 3/4 of the work is completed. Then how many persons should he remove so that the project will be completed in stipulated time?
View Solution