Had work been resumed by the labourers before the manager arrived?
Have the labourers resumed work before the arrived of the manager?
Had the labourers resumed work before the manager arrived?
Had they resumed the work before the manager came?
Had the labourers not resumed work before the manager arrived?
The correct Answer is:B
Had the labourers resumed work before the manager arrived? (Active)
Similar Questions
Knowledge Check
- Question 1 - Select One
Select the most appropriate option to improve the underlined segment in the given sentence. If there is no need to improve it, select No improvement.
The meeting will start when the manager is arriving.AarrivesBNo improvementCarrivedDwas arrived - Question 2 - Select One
The pilots had been warned about the storm before they took . . . . .
AawayBupCoverDoff - Question 3 - Select One
Our task had been completed before the deadline.
AThe task was completed by us before the deadline.BBefore the deadline we had to complete our task.CThe task had been completed by us before the deadline.DWe had completed our task before the deadline.
Voltech Ltd. Is engaged in producing electricity from demesitic grabage. There is almost equal division of work and responsibility between workers and management. The management even takes workers into confidence before taking important dicisions. All the workeers are satisfied as the behaviour of management is good.
State the principles of management discribed in above para.View SolutionRewrite the sentence into active voice.
He will have been done this work before you leave.View SolutionThe difference between labour force and work force is-
View SolutionA Contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realised that the work would get delayed by three-fourth of the scheduled time, so he at once doubled the no of workers and thus he managed to finish the road on the scheduled time. How much work he had been completed, before increasing the number of workers?
View SolutionA Contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realised that the work would get delayed by three-fourth of the scheduled time, so he at once doubled the no of workers and thus he managed to finish the road on the scheduled time. How much work he had been completed, before increasing the number of workers?
View Solution