30 labourers working 7 hours a day can finish a piece of work in 18 days. If the labourers work 6 hours a day, then the number of labourers to finish the same piece of work in30 days, will be: 15 b. 21 c. 22 d. 25
To solve the problem step by step, we will use the concept of work done, which is based on the number of laborers, the hours they work, and the number of days they work.
Step 1: Calculate the total work done in terms of labor-hours.
The total work can be calculated using the formula:
Total Work=Number of Laborers×Hours per Day×Days
Given:
- Number of laborers = 30
- Hours per day = 7
- Days = 18
So, the total work done is:
Total Work=30×7×18
Step 2: Calculate the total work.
Now, we will calculate the total work:
Total Work=30×7×18=3780 labor-hours
Step 3: Set up the equation for the new scenario.
Now, we need to find out how many laborers (let's denote this as x) are required to complete the same amount of work (3780 labor-hours) if they work 6 hours a day for 30 days.
Using the same formula for total work:
Total Work=x×Hours per Day×Days
3780=x×6×30
Step 4: Solve for x.
Now we can solve for x:
3780=x×180
x=3780180
Step 5: Calculate x.
Now we will calculate x:
x=21
Conclusion:
Therefore, the number of laborers required to finish the same piece of work in 30 days, working 6 hours a day, is 21.
The total work can be calculated using the formula:
Total Work=Number of Laborers×Hours per Day×Days
- Number of laborers = 30
- Hours per day = 7
- Days = 18
Total Work=30×7×18
Now, we will calculate the total work:
Total Work=30×7×18=3780 labor-hours
Now, we need to find out how many laborers (let's denote this as x) are required to complete the same amount of work (3780 labor-hours) if they work 6 hours a day for 30 days.
Total Work=x×Hours per Day×Days
3780=x×6×30
Now we can solve for x:
3780=x×180
x=3780180
Now we will calculate x:
x=21
Therefore, the number of laborers required to finish the same piece of work in 30 days, working 6 hours a day, is 21.
Topper's Solved these Questions
Similar Questions
If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
View SolutionWorking 7 hours in a day, 4 men can do a piece of work in 8 days. Working 8 hours in a day, the required number of men to perform the same work in 4 days will be
View Solution
Knowledge Check
- Question 1 - Select One
24 men working 8 hours a day can finish a work in 10 days. Working at the rate of 10 hours a day, the number of men required to finish the same work in 6 days is:
Aa. 30Bb. 32Cc. 34Dd. 36 - Question 2 - Select One
Working 10 hours a day, Aman can complete a piece of work in 18 days. How many hours a day should he work so as to finish the work in 15 days ?
A10B12C16D18 - Question 3 - Select One
If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
A15 5/21 daysB11 2/3 daysC6 9/16 daysD4 1/5 days
A and B together can do a piece of work in 6 days. If A can
alone do the work in 18 days, hen the number of days
required for B to finish the work isView SolutionWorking 15 hours a day, Goldy can complete a piece of work in 24 days. How many hours a day he should work so as to finish the work in 18 days?
View SolutionWorking 15 hours a day, Goldy can complete a piece of work in 24 days. How many hours a day he should work so as to finish the work in 18 days?
View SolutionWorking 6 hours a day, Raman can complete a piece of work in 24 days. How many hours a day should he work so as to finish the work in 18 days?
View SolutionIf 28 men working 8 hours per day can finish a piece of work in 10 days. How many hours per day 40 men must work to complete the same work in 8 days.
View Solution