A can do a work in 15 days and B in 30 days. If they work on it together, then in how many days will they be able to do 50% of the work?
5 days
6 days
4 days
3 days
To solve the problem step-by-step, we will follow the outlined approach:
Step 1: Determine the work done by A and B individually.
- A can complete the work in 15 days.
- B can complete the work in 30 days.
Step 2: Calculate the efficiency of A and B.
- Efficiency of A = Total Work / Time taken by A = 1 work unit / 15 days = 1/15 work units per day.
- Efficiency of B = Total Work / Time taken by B = 1 work unit / 30 days = 1/30 work units per day.
Step 3: Find the combined efficiency of A and B.
- Combined Efficiency = Efficiency of A + Efficiency of B
- Combined Efficiency = (1/15) + (1/30)
To add these fractions, we need a common denominator:
- The least common multiple (LCM) of 15 and 30 is 30.
- Convert (1/15) to (2/30) to have a common denominator.
So,
- Combined Efficiency = (2/30) + (1/30) = (3/30) = 1/10 work units per day.
Step 4: Calculate the total work needed for 50% of the work.
- Total work = 1 work unit, so 50% of the work = 1/2 work unit.
Step 5: Determine the time taken to complete 50% of the work.
- Time = Work / Efficiency
- Time = (1/2) / (1/10) = (1/2) * (10/1) = 5 days.
Conclusion:
If A and B work together, they will be able to complete 50% of the work in 5 days.
---
- A can complete the work in 15 days.
- B can complete the work in 30 days.
- Efficiency of A = Total Work / Time taken by A = 1 work unit / 15 days = 1/15 work units per day.
- Efficiency of B = Total Work / Time taken by B = 1 work unit / 30 days = 1/30 work units per day.
- Combined Efficiency = Efficiency of A + Efficiency of B
- Combined Efficiency = (1/15) + (1/30)
- The least common multiple (LCM) of 15 and 30 is 30.
- Convert (1/15) to (2/30) to have a common denominator.
- Combined Efficiency = (2/30) + (1/30) = (3/30) = 1/10 work units per day.
- Total work = 1 work unit, so 50% of the work = 1/2 work unit.
- Time = Work / Efficiency
- Time = (1/2) / (1/10) = (1/2) * (10/1) = 5 days.
If A and B work together, they will be able to complete 50% of the work in 5 days.
Similar Questions
Knowledge Check
- Question 1 - Select One
A can do a work in 36 days and B in 12 days. If they work to gether in how many days will they be able to do the work?
A8B6C10D9 - Question 2 - Select One
A can do a work in 15 days and B in 20 days. If they together work on it for 4 days, then the fraction of the work that is left is :
A815B715C14D110 - Question 3 - Select One
A can complete a piece of work in 20 days and B can complete 20% of the work in 6 days. If they work together in how many days can they finish 50% of the work, if they work together?
A12B6C8D9
If A can do a work in 10 days and B can do the same work in 15 days, then how many days will they take to complete the work both while working together?
View SolutionIf A can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days , then working together , how many days will they take to complete the work ?
View SolutionA can do a piece of work in 15 days and B in 20 days. If they together work on it for 4 days, then the fraction of the work that is left is :
View SolutionA can do a work in 15 days and B in 20 days.If they together work on it for 4 days, then the fraction of the work that is left is:
View SolutionIf A alone can do a work in 12 days and B alone can do it in 8 days, Working together, in how many days will they complete it?
View Solution