P and Q can do a job in 2 days, Q and R can do it in 4 days, and P and R in 12/5 days. What is the number of days required for P alone to do the job?

A

5/2

B

3

C

14/5

D

6

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will use the information given about the work done by P, Q, and R together.

Step 1: Determine the total work
We know:
- P and Q can complete the job in 2 days.
- Q and R can complete the job in 4 days.
- P and R can complete the job in 125 days.

To find a common measure of work, we can take the least common multiple (LCM) of the days taken by each pair to complete the job.

The LCM of 2, 4, and 125 can be calculated as follows:
- Convert 125 to a decimal or fraction that can be easily compared: 125=2.4.
- The LCM of 2, 4, and 2.4 is 12.

Thus, we can assume the total work is 12 units.

Step 2: Calculate the efficiencies
Now, we will calculate the work done per day by each pair:
- For P and Q: If they complete 12 units in 2 days, their combined efficiency is:
Efficiency of P + Q=12 units2 days=6 units/day

- For Q and R: If they complete 12 units in 4 days, their combined efficiency is:
Efficiency of Q + R=12 units4 days=3 units/day

- For P and R: If they complete 12 units in 125 days, their combined efficiency is:
Efficiency of P + R=12 units125 days=5 units/day

Step 3: Set up equations
Let:
- Efficiency of P = p
- Efficiency of Q = q
- Efficiency of R = r

From the efficiencies calculated, we have the following equations:
1. p+q=6 (from P and Q)
2. q+r=3 (from Q and R)
3. p+r=5 (from P and R)

Step 4: Solve the equations
We can solve these equations step by step.

From equation (1):
q=6p

Substituting q in equation (2):
(6p)+r=3r=36+pr=p3

Now substituting r in equation (3):
p+(p3)=52p3=52p=8p=4

Step 5: Find the time taken by P alone
Now that we have p=4 (the efficiency of P), we can find out how many days P will take to complete the job alone:
Time taken by P=Total WorkEfficiency of P=12 units4 units/day=3 days

Final Answer
Thus, P alone will take 3 days to complete the job.

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A and B can do a job in 12 days, B and C in 15 days and C and A in 20 days. How long would A take to do that work?

    A20 days
    B60 days
    C30 days
    D40 days
  • P and Q can complete a work in 18 days, Q and R in 24 days and P and R in 36 days. What will be the ratio of efficiency of P, Q and R respectively?

    A3:5:1
    B4:3:2
    C3:4:6
    D2:3:5
  • Working together, P and Q can do a job in 6 days, Q and R can do the same job in 10 days while P and R can do it in 5 days How long will it take, if all of them work together to complete the job?

    A427 days
    B437 days
    C447 days
    D457 days