Find the number of days in which Q can do a job if P can do the same job in 8 days.
A. Q is 60% more efficient than P.
B. P and Q togetyher can do the job in 10/3 days.
C. P is 75/2% less efficient than Q.
only A is sufficient
Only B is sufficient
Either A or B is sufficient
Any of them
The correct Answer is:D
To find the number of days in which Q can do a job if P can do the same job in 8 days, we will analyze the information provided in each case (A, B, and C) step by step.
Step 1: Understanding the efficiency of P
P can complete the job in 8 days. Therefore, P's work rate is:
Work rate of P=1 job8 days=18 jobs per day
Step 2: Analyzing Case A
Case A: Q is 60% more efficient than P.
If Q is 60% more efficient than P, we can calculate Q's work rate as follows:
Efficiency of Q=Efficiency of P+60% of Efficiency of P
Efficiency of Q=18+0.6×18=18+0.68=1+0.68=1.68=0.21=15 jobs per day
Now, to find the number of days Q takes to complete the job:
Days taken by Q=1 jobWork rate of Q=115=5 days
Step 3: Analyzing Case B
Case B: P and Q together can do the job in 103 days.
To find their combined work rate:
Combined work rate=1 job103 days=310 jobs per day
Let Q's work rate be x. Then:
Work rate of P+Work rate of Q=18+x=310
Solving for x:
x=310−18
Finding a common denominator (40):
x=1240−540=740 jobs per day
Now, to find the number of days Q takes to complete the job:
Days taken by Q=1 jobx=1740=407 days≈5.71 days
Step 4: Analyzing Case C
Case C: P is 752% less efficient than Q.
This means:
Efficiency of P=Efficiency of Q−752% of Efficiency of Q
Let Q's efficiency be y:
18=y−75200y=y(1−75200)=y(125200)=58y
Now solving for y:
y=1/85/8=15 jobs per day
Now, to find the number of days Q takes to complete the job:
Days taken by Q=1 joby=115=5 days
Conclusion
From the analysis of all three cases:
- Case A: Q takes 5 days.
- Case B: Q takes approximately 5.71 days.
- Case C: Q takes 5 days.
Thus, Cases A and C provide a definitive answer that Q can complete the job in 5 days.
P can complete the job in 8 days. Therefore, P's work rate is:
Work rate of P=1 job8 days=18 jobs per day
Case A: Q is 60% more efficient than P.
Efficiency of Q=Efficiency of P+60% of Efficiency of P
Efficiency of Q=18+0.6×18=18+0.68=1+0.68=1.68=0.21=15 jobs per day
Days taken by Q=1 jobWork rate of Q=115=5 days
Case B: P and Q together can do the job in 103 days.
Combined work rate=1 job103 days=310 jobs per day
Work rate of P+Work rate of Q=18+x=310
x=310−18
Finding a common denominator (40):
x=1240−540=740 jobs per day
Days taken by Q=1 jobx=1740=407 days≈5.71 days
Case C: P is 752% less efficient than Q.
Efficiency of P=Efficiency of Q−752% of Efficiency of Q
Let Q's efficiency be y:
18=y−75200y=y(1−75200)=y(125200)=58y
y=1/85/8=15 jobs per day
Days taken by Q=1 joby=115=5 days
From the analysis of all three cases:
- Case A: Q takes 5 days.
- Case B: Q takes approximately 5.71 days.
- Case C: Q takes 5 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
A can do a certain job in 12 days. B is 60% more efficient than A. Then B can do the same piece of work in
A8 daysB712 daysC614 daysD6 days - Question 2 - Select One
A can do a certain job in 12 days. B is 60% more efficient than A. To do the same job B alone would take?
A712 daysB8 daysC10 daysD7 days - Question 3 - Select One
P can do a work in 9 days and Q is 50% more efficient than P. In how many days can Q do it alone ?
A1312B412C6D3
A can do a job in 12 days and B can do the same job in 6 days, in how many days working together they can complete the job?
View SolutionA can do a piece of work in 24 days. If B is 60% more efficient than A, then how many days does B require to do the same work?
View SolutionP can do a piece of work in 36 days. If Q is 50% more efficient than P, then in how many days can Q do the same work?
View SolutionP alone can do a work in 25 days. P is 40% less efficient than Q. In how many days can Q alone do the work?
View SolutionA alone can do a work in 15 days. A is 20% less efficient than B. In how many days can B alone do the work?
View Solution