Doubtnut Promotions Sticky

Find the number of days in which Q can do a job if P can do the same job in 8 days.
A. Q is 60% more efficient than P.
B. P and Q togetyher can do the job in 10/3 days.
C. P is 75/2% less efficient than Q.

A

only A is sufficient

B

Only B is sufficient

C

Either A or B is sufficient

D

Any of them

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To find the number of days in which Q can do a job if P can do the same job in 8 days, we will analyze the information provided in each case (A, B, and C) step by step.

Step 1: Understanding the efficiency of P
P can complete the job in 8 days. Therefore, P's work rate is:
Work rate of P=1 job8 days=18 jobs per day

Step 2: Analyzing Case A
Case A: Q is 60% more efficient than P.

If Q is 60% more efficient than P, we can calculate Q's work rate as follows:
Efficiency of Q=Efficiency of P+60% of Efficiency of P
Efficiency of Q=18+0.6×18=18+0.68=1+0.68=1.68=0.21=15 jobs per day

Now, to find the number of days Q takes to complete the job:
Days taken by Q=1 jobWork rate of Q=115=5 days

Step 3: Analyzing Case B
Case B: P and Q together can do the job in 103 days.

To find their combined work rate:
Combined work rate=1 job103 days=310 jobs per day

Let Q's work rate be x. Then:
Work rate of P+Work rate of Q=18+x=310

Solving for x:
x=31018
Finding a common denominator (40):
x=1240540=740 jobs per day

Now, to find the number of days Q takes to complete the job:
Days taken by Q=1 jobx=1740=407 days5.71 days

Step 4: Analyzing Case C
Case C: P is 752% less efficient than Q.

This means:
Efficiency of P=Efficiency of Q752% of Efficiency of Q
Let Q's efficiency be y:
18=y75200y=y(175200)=y(125200)=58y

Now solving for y:
y=1/85/8=15 jobs per day

Now, to find the number of days Q takes to complete the job:
Days taken by Q=1 joby=115=5 days

Conclusion
From the analysis of all three cases:
- Case A: Q takes 5 days.
- Case B: Q takes approximately 5.71 days.
- Case C: Q takes 5 days.

Thus, Cases A and C provide a definitive answer that Q can complete the job in 5 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do a certain job in 12 days. B is 60% more efficient than A. Then B can do the same piece of work in

    A8 days
    B712 days
    C614 days
    D6 days
  • Question 2 - Select One

    A can do a certain job in 12 days. B is 60% more efficient than A. To do the same job B alone would take?

    A712 days
    B8 days
    C10 days
    D7 days
  • Question 3 - Select One

    P can do a work in 9 days and Q is 50% more efficient than P. In how many days can Q do it alone ?

    A1312
    B412
    C6
    D3