A and B can do a piece of work in 8 days. B and C can do it in 24 days, while C and A can do it in 847 days. In how many days can C do it alone?
60
40
50
10
The correct Answer is:A
To solve the problem step by step, we will first determine the work done by A, B, and C based on the information given.
Step 1: Determine the work done by A and B together
A and B can complete the work in 8 days. Therefore, the fraction of work done by A and B in one day is:
Work done by A and B in one day=18
Step 2: Determine the work done by B and C together
B and C can complete the work in 24 days. Therefore, the fraction of work done by B and C in one day is:
Work done by B and C in one day=124
Step 3: Determine the work done by C and A together
C and A can complete the work in 847 days. First, convert 847 to an improper fraction:
847=607 days
Thus, the fraction of work done by C and A in one day is:
Work done by C and A in one day=1607=760
Step 4: Set up equations for the work done
Let the work done by A in one day be a, by B be b, and by C be c. We can write the following equations based on the work done:
1. a+b=18 (Equation 1)
2. b+c=124 (Equation 2)
3. c+a=760 (Equation 3)
Step 5: Add the equations
Adding all three equations:
(a+b)+(b+c)+(c+a)=18+124+760
This simplifies to:
2a+2b+2c=18+124+760
Now, we need to find a common denominator to add the fractions on the right side. The least common multiple of 8, 24, and 60 is 120.
Converting each fraction:
- 18=15120
- 124=5120
- 760=14120
Now, adding these fractions:
15120+5120+14120=34120
Step 6: Simplify the equation
So we have:
2(a+b+c)=34120
Dividing both sides by 2:
a+b+c=17120
Step 7: Find the value of C's work
From Equation 1, we know:
a+b=18=15120
Now substituting into the equation:
c=(a+b+c)−(a+b)=17120−15120=2120=160
Step 8: Calculate the time taken by C to complete the work alone
If C does 160 of the work in one day, then the number of days C will take to complete the entire work is the reciprocal:
Days taken by C=1160=60 days
Final Answer
C can complete the work alone in 60 days.
A and B can complete the work in 8 days. Therefore, the fraction of work done by A and B in one day is:
Work done by A and B in one day=18
B and C can complete the work in 24 days. Therefore, the fraction of work done by B and C in one day is:
Work done by B and C in one day=124
C and A can complete the work in 847 days. First, convert 847 to an improper fraction:
847=607 days
Thus, the fraction of work done by C and A in one day is:
Work done by C and A in one day=1607=760
Let the work done by A in one day be a, by B be b, and by C be c. We can write the following equations based on the work done:
1. a+b=18 (Equation 1)
2. b+c=124 (Equation 2)
3. c+a=760 (Equation 3)
Adding all three equations:
(a+b)+(b+c)+(c+a)=18+124+760
This simplifies to:
2a+2b+2c=18+124+760
Now, we need to find a common denominator to add the fractions on the right side. The least common multiple of 8, 24, and 60 is 120.
- 18=15120
- 124=5120
- 760=14120
15120+5120+14120=34120
So we have:
2(a+b+c)=34120
Dividing both sides by 2:
a+b+c=17120
From Equation 1, we know:
a+b=18=15120
Now substituting into the equation:
c=(a+b+c)−(a+b)=17120−15120=2120=160
If C does 160 of the work in one day, then the number of days C will take to complete the entire work is the reciprocal:
Days taken by C=1160=60 days
C can complete the work alone in 60 days.
Topper's Solved these Questions
Similar Questions
A and B can do a piece of work in 9 days; B and C can do it in 12 days; A and C can do it in 18 days. In how many days will A, B and C finish it working together and separately?
View SolutionA and C can do a work in 12 days while A,B and C can do the work in 4 days. In how many days can B do the work alone?
View Solution
Knowledge Check
- Question 1 - Select One
A and B can do a piece of work in S days. B and C can do it in 24 days while C and A can do it in 8(47) days. In how many days can C do it alone?
A60B40C30D10 - Question 2 - Select One
A and B can do a piece of work in 72 days, B and C can do it in 120 days while A and C can do it in 90 days. In what time can A alone do it?
A80 daysB100 daysC120 daysD150 days - Question 3 - Select One
A and B can do a piece of work in 72 days B and C can do it in 120 days. A and C can do it in 90 days. In how many days, all the three together can do the work?
A80 daysB100 daysC60 daysD150 days
A and B can do a piece of wok in 72 days, B and C can do it in 120 days, A and C can do it in 90 days. In what time can A alone do it ?
View SolutionA and B together can do a piece of work in 12 days; B and C can do it in 20 days while C and A can do it in 15 days. A, B and C all working together can do it in
View SolutionA and B can do a piece of work in 10 days, B and C can do it in 12 days. C and A in 15 days. In how many days will c finish it alone?
View SolutionA and B can do a piece of work in 8 days, B and C can do the same work in 12 days and A and C complete it in 8 days. In how many days A, B and C can complete the whole work, working together?
View SolutionA and B can do a work in 12 days, B and C can do the same work in 15 days & C and A can do it in 20 days. In how many days they can do it separately?
View Solution