A and B can do a piece of work in 8 days, B and C can do the same work in 12 days and A and C complete it in 8 days. In how many days A, B and C can complete the whole work, working together?
4
6
12
9
The correct Answer is:B
To solve the problem step by step, we will first determine the efficiencies of A, B, and C based on the information provided.
Step 1: Determine the efficiencies of pairs A & B, B & C, and A & C
- A and B can complete the work in 8 days. Therefore, their combined efficiency is:
Efficiency of A and B=1 work8 days=18
- B and C can complete the work in 12 days. Therefore, their combined efficiency is:
Efficiency of B and C=1 work12 days=112
- A and C can complete the work in 8 days. Therefore, their combined efficiency is:
Efficiency of A and C=1 work8 days=18
Step 2: Set up equations based on efficiencies
Let the efficiencies of A, B, and C be represented as a, b, and c respectively. We can set up the following equations based on the efficiencies calculated:
1. a+b=18 (from A and B)
2. b+c=112 (from B and C)
3. a+c=18 (from A and C)
Step 3: Solve the equations
We can solve these equations to find the individual efficiencies of A, B, and C.
From equation (1):
a+b=18(1)
From equation (3):
a+c=18(3)
Subtract equation (1) from equation (3):
(a+c)−(a+b)=18−18
c−b=0⟹c=b(4)
Now substitute c=b into equation (2):
b+b=112
2b=112⟹b=124
Now substitute b back into equation (4) to find c:
c=124
Now substitute b into equation (1) to find a:
a+124=18
Convert 18 to a fraction with a denominator of 24:
18=324
Thus,
a+124=324⟹a=324−124=224=112
Step 4: Calculate the total efficiency of A, B, and C
Now we have:
- a=112
- b=124
- c=124
The total efficiency of A, B, and C working together is:
Total Efficiency=a+b+c=112+124+124
To add these fractions, we need a common denominator, which is 24:
112=224
Thus,
Total Efficiency=224+124+124=424=16
Step 5: Calculate the time taken by A, B, and C to complete the work
The time taken to complete the work is the reciprocal of the total efficiency:
Time=1Total Efficiency=116=6 days
Final Answer
A, B, and C can complete the whole work together in 6 days.
---
- A and B can complete the work in 8 days. Therefore, their combined efficiency is:
Efficiency of A and B=1 work8 days=18
Efficiency of B and C=1 work12 days=112
Efficiency of A and C=1 work8 days=18
Let the efficiencies of A, B, and C be represented as a, b, and c respectively. We can set up the following equations based on the efficiencies calculated:
2. b+c=112 (from B and C)
3. a+c=18 (from A and C)
We can solve these equations to find the individual efficiencies of A, B, and C.
a+b=18(1)
a+c=18(3)
(a+c)−(a+b)=18−18
c−b=0⟹c=b(4)
b+b=112
2b=112⟹b=124
c=124
a+124=18
Convert 18 to a fraction with a denominator of 24:
18=324
Thus,
a+124=324⟹a=324−124=224=112
Now we have:
- a=112
- b=124
- c=124
Total Efficiency=a+b+c=112+124+124
112=224
Thus,
Total Efficiency=224+124+124=424=16
The time taken to complete the work is the reciprocal of the total efficiency:
Time=1Total Efficiency=116=6 days
A, B, and C can complete the whole work together in 6 days.
Topper's Solved these Questions
- BOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - EXERCISE(LEVEL 2)55videos
TIME AND WORK
- BOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round15videos
TIME AND WORK
- BOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round15videos
TIME AND WORK
- BOOK - ARIHANT SSCCHAPTER - THEORY OF EQUATIONSEXERCISE - EXERCISE(LEVEL 2)20videos
THEORY OF EQUATIONS
- BOOK - ARIHANT SSCCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - SPEED TEST (TSD)10videos
TIME, SPEED AND DISTANCE
Similar Questions
A and B can do a piece of work in 8 days, B and C can do the same work in 12 days. If A, B and C can complete the same work in 6 days, in how many days can A and C complete the same work?
View SolutionA and B can do a piece of work in 8 days, B and C can do the same work in 12 days. If A, B and C can complete the same work in 6 days, in how many days can A and C complete the same work?
View Solution
Knowledge Check
- Question 1 - Select One
P and Q can do a piece of work in 8 days, Q and R can do the same work in 12 days and P and R complete it in 8 days In how many days can P,Q and R complete the whole work, working together?
A4B6C12D9 - Question 2 - Select One
A and B can do a piece of work in 8 days, B and C can do the same work in 12 days and A and C complete it in 8 days. In how many days A, B and C can complete the whole work, working together?
A8B10C12D16 - Question 3 - Select One
A and B can do a piece of work in 8 days. B and C can do it in 24 days, while C and A can do it in 847 days. In how many days can C do it alone?
A60B40C50D10
A and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and C can do the same in 12 days. Time taken by A, B and C together to do the job is
View SolutionA and B can do a given piece of work in 8 days, B and C can do the same work in 12 days and A, B, C complete it in 6 days. Number of days required to finish the work by A and C is
View SolutionB and C can do a work in 12 days. C and D can do the same work in 18 days. D and B can do the same work in 24 days. In how many days can B, C and D together complete the work?
View SolutionA and B can do a piece of work in 72 days B and C can do it in 120 days. A and C can do it in 90 days. In how many days, all the three together can do the work?
View SolutionA and B can do a work in 30 days, B and C can do it in 36 days and C and A can do the same work in 45 days. In how many days A, B and C can do this work together?
View Solution