A is thrice as efficient as B and hence completes a work in 40 days less than the number of days taken by B. What will be the number of days taken by both of them when working together?
22.5 days
15 days
20 days
18 days
To solve the problem step by step, let's denote the number of days taken by A to complete the work as x days and the number of days taken by B to complete the work as 3x days (since A is thrice as efficient as B).
Step 1: Set up the equation based on the information given.
According to the problem, A completes the work in 40 days less than B. Therefore, we can write the equation as:
x=3x−40
Step 2: Solve for x.
Rearranging the equation:
x−3x=−40
−2x=−40
Dividing both sides by -2:
x=20
Step 3: Determine the number of days taken by B.
Since we have found x, we can now find the number of days B takes to complete the work:
3x=3×20=60 days
Step 4: Calculate the work done by A and B together.
To find out how many days A and B will take to complete the work together, we need to calculate their combined work rate. The work done by A in one day is:
1x=120
And the work done by B in one day is:
13x=160
Step 5: Add their work rates together.
Now, we can add their work rates:
Combined work rate=120+160
To add these fractions, we need a common denominator. The least common multiple of 20 and 60 is 60:
120=360
Thus,
Combined work rate=360+160=460=115
Step 6: Calculate the time taken to complete the work together.
If their combined work rate is 115, it means they can complete the work in:
Time=1Combined work rate=15 days
Final Answer:
A and B together will complete the work in 15 days.
According to the problem, A completes the work in 40 days less than B. Therefore, we can write the equation as:
x=3x−40
Rearranging the equation:
x−3x=−40
−2x=−40
Dividing both sides by -2:
x=20
Since we have found x, we can now find the number of days B takes to complete the work:
3x=3×20=60 days
To find out how many days A and B will take to complete the work together, we need to calculate their combined work rate. The work done by A in one day is:
1x=120
And the work done by B in one day is:
13x=160
Now, we can add their work rates:
Combined work rate=120+160
To add these fractions, we need a common denominator. The least common multiple of 20 and 60 is 60:
120=360
Thus,
Combined work rate=360+160=460=115
If their combined work rate is 115, it means they can complete the work in:
Time=1Combined work rate=15 days
A and B together will complete the work in 15 days.
Similar Questions
If X works 3 tims as fast as Y and is able to complete, a work in 40 days less than the number of days taken by Y, then find the time in which they cn complete the work working together.
View SolutionX works 3 times as fast as Y and is able to complete a work in40 days less than the number of days taken by Y. Find the time in which they can complete the work together.
View Solution
Knowledge Check
A is thrice as efficient as B and hence completes a work in 40
days less than the number days taken by B. What will be
the number of days taken by both of them when working
together ?A22.5 daysB15 daysC20 daysD18 daysA is thrice as efficient as B. Working together they complete the work in 3 days. If B takes 8 days more than A, what is the number of days taken by A to finish the whole work, alone ?
A4B2C12D16A is thrice as efficient as B.A and B cam complete a piece of work in 12 days. Find the number of days in which A alone complete it.
A48B16C20D32
X works 3 times as fast as Y and is able to complete a work in40 days less than the number of days taken by Y. Find the time in which they can complete the work together.
View SolutionIf A is twice as efficient as B, and A and B together can complete a work in 20 days, then find the number of days in which B can do the work alone.
(a)60 days
(b) 50 days
(c)30 days
(d)40 days
View SolutionA is thrice as efficient as B. If B takes 8 days more than A, what is the number of days taken by A to finish the whole work, alone?
View SolutionA is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.
View SolutionA is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.
View Solution