The ratio of efficiency of A is to C is 5:3. The ratio of number of days taken by B is to C is 2:3. A takes 6 days less than C, when A and C completes the work individually. B and C started the work and left after 2 days. The number of days taken by A to finish the remaining work is :

A

4.5

B

5

C

6

D

913

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, let's break down the information provided and calculate the required values.

Step 1: Understand the efficiency ratios
- The efficiency ratio of A to C is given as 5:3.
- This means if A's efficiency is 5x, then C's efficiency is 3x.

Step 2: Determine the time ratios
- The time taken by A and C will be the inverse of their efficiencies. Therefore, the time ratio of A to C is:
Time ratio of A to C=35
- Let the time taken by C be 5y days. Then, the time taken by A will be 3y days.

Step 3: Relate A's and C's time
- It is given that A takes 6 days less than C:
5y3y=62y=6y=3
- Therefore, the time taken by C is:
5y=5×3=15 days
- And the time taken by A is:
3y=3×3=9 days

Step 4: Determine the efficiency of B
- The ratio of the number of days taken by B to C is 2:3. Thus, if C takes 15 days, then B takes:
Time taken by B=23×15=10 days
- The efficiency of B will then be:
Efficiency of B=110 of the work per day
- Since C takes 15 days, C's efficiency is:
Efficiency of C=115 of the work per day

Step 5: Calculate total work
- The total work can be calculated using A's efficiency:
Total work=Efficiency of A×Time taken by A=5×9=45 units

Step 6: Work done by B and C in 2 days
- B and C work together for 2 days:
Work done in 2 days=(Bs efficiency+Cs efficiency)×2
- B's efficiency is 110 and C's efficiency is 115:
Work done in 2 days=(110+115)×2
- To add these fractions, find a common denominator (30):
=(330+230)×2=(530)×2=16×2=13 of the total work
- Thus, the work done in 2 days is:
=13×45=15 units

Step 7: Remaining work
- The remaining work after 2 days is:
Remaining work=4515=30 units

Step 8: Time taken by A to finish remaining work
- A's efficiency is 5 units per day, so the time taken by A to finish the remaining work is:
Time taken by A=Remaining workEfficiency of A=305=6 days

Final Answer
The number of days taken by A to finish the remaining work is 6 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • The ratio of efficiency of A is to C is.5 :3 The ratio of number of days taken by B is to C is 2:3 . A takes 6 days less than C, when A and C completes the work individually. B and C started the work arid left after 3 days. The number of days taken by A to finish the remaining work is:

    A4.5
    B5
    C6
    D913
  • A can do a piece of work in 12 days and B in 15 days. They work together for 5 days and then B left. The days taken by A to finish the remaining work is

    A3
    B5
    C10
    D121
  • The rates of working of A and B are in the ratio 3:4.The number of days taken by them to finish the work are in the ratio

    A3:4
    B9:16
    C4:3
    DNone of these