The ratio of efficiency of A is to C is 5:3. The ratio of number of days taken by B is to C is 2:3. A takes 6 days less than C, when A and C completes the work individually. B and C started the work and left after 2 days. The number of days taken by A to finish the remaining work is :
4.5
5
6
913
The correct Answer is:C
To solve the problem step by step, let's break down the information provided and calculate the required values.
Step 1: Understand the efficiency ratios
- The efficiency ratio of A to C is given as 5:3.
- This means if A's efficiency is 5x, then C's efficiency is 3x.
Step 2: Determine the time ratios
- The time taken by A and C will be the inverse of their efficiencies. Therefore, the time ratio of A to C is:
Time ratio of A to C=35
- Let the time taken by C be 5y days. Then, the time taken by A will be 3y days.
Step 3: Relate A's and C's time
- It is given that A takes 6 days less than C:
5y−3y=6⟹2y=6⟹y=3
- Therefore, the time taken by C is:
5y=5×3=15 days
- And the time taken by A is:
3y=3×3=9 days
Step 4: Determine the efficiency of B
- The ratio of the number of days taken by B to C is 2:3. Thus, if C takes 15 days, then B takes:
Time taken by B=23×15=10 days
- The efficiency of B will then be:
Efficiency of B=110 of the work per day
- Since C takes 15 days, C's efficiency is:
Efficiency of C=115 of the work per day
Step 5: Calculate total work
- The total work can be calculated using A's efficiency:
Total work=Efficiency of A×Time taken by A=5×9=45 units
Step 6: Work done by B and C in 2 days
- B and C work together for 2 days:
Work done in 2 days=(B′s efficiency+C′s efficiency)×2
- B's efficiency is 110 and C's efficiency is 115:
Work done in 2 days=(110+115)×2
- To add these fractions, find a common denominator (30):
=(330+230)×2=(530)×2=16×2=13 of the total work
- Thus, the work done in 2 days is:
=13×45=15 units
Step 7: Remaining work
- The remaining work after 2 days is:
Remaining work=45−15=30 units
Step 8: Time taken by A to finish remaining work
- A's efficiency is 5 units per day, so the time taken by A to finish the remaining work is:
Time taken by A=Remaining workEfficiency of A=305=6 days
Final Answer
The number of days taken by A to finish the remaining work is 6 days.
---
- The efficiency ratio of A to C is given as 5:3.
- This means if A's efficiency is 5x, then C's efficiency is 3x.
- The time taken by A and C will be the inverse of their efficiencies. Therefore, the time ratio of A to C is:
Time ratio of A to C=35
- Let the time taken by C be 5y days. Then, the time taken by A will be 3y days.
- It is given that A takes 6 days less than C:
5y−3y=6⟹2y=6⟹y=3
- Therefore, the time taken by C is:
5y=5×3=15 days
- And the time taken by A is:
3y=3×3=9 days
- The ratio of the number of days taken by B to C is 2:3. Thus, if C takes 15 days, then B takes:
Time taken by B=23×15=10 days
- The efficiency of B will then be:
Efficiency of B=110 of the work per day
- Since C takes 15 days, C's efficiency is:
Efficiency of C=115 of the work per day
- The total work can be calculated using A's efficiency:
Total work=Efficiency of A×Time taken by A=5×9=45 units
- B and C work together for 2 days:
Work done in 2 days=(B′s efficiency+C′s efficiency)×2
- B's efficiency is 110 and C's efficiency is 115:
Work done in 2 days=(110+115)×2
- To add these fractions, find a common denominator (30):
=(330+230)×2=(530)×2=16×2=13 of the total work
- Thus, the work done in 2 days is:
=13×45=15 units
- The remaining work after 2 days is:
Remaining work=45−15=30 units
- A's efficiency is 5 units per day, so the time taken by A to finish the remaining work is:
Time taken by A=Remaining workEfficiency of A=305=6 days
The number of days taken by A to finish the remaining work is 6 days.
Topper's Solved these Questions
- BOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - EXERCISE(LEVEL 2)55videos
TIME AND WORK
- BOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round15videos
TIME AND WORK
- BOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round15videos
TIME AND WORK
- BOOK - ARIHANT SSCCHAPTER - THEORY OF EQUATIONSEXERCISE - EXERCISE(LEVEL 2)20videos
THEORY OF EQUATIONS
- BOOK - ARIHANT SSCCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - SPEED TEST (TSD)10videos
TIME, SPEED AND DISTANCE
Similar Questions
The rates of working of A and B are in the ratio 3:4.The number of days taken by them to finish the work are in the ratio
View SolutionA can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but they are forced to leave after 3 days. The remaining work was done by A in
View Solution
Knowledge Check
- Question 1 - Select One
The ratio of efficiency of A is to C is.5 :3 The ratio of number of days taken by B is to C is 2:3 . A takes 6 days less than C, when A and C completes the work individually. B and C started the work arid left after 3 days. The number of days taken by A to finish the remaining work is:
A4.5B5C6D913 - Question 2 - Select One
A can do a piece of work in 12 days and B in 15 days. They work together for 5 days and then B left. The days taken by A to finish the remaining work is
A3B5C10D121 - Question 3 - Select One
The rates of working of A and B are in the ratio 3:4.The number of days taken by them to finish the work are in the ratio
A3:4B9:16C4:3DNone of these
A can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be
View SolutionThe rates of working of A and B are In the ratio of 2:3. The number of days taken by each of them to finish the work is in the ratio:
View SolutionA is thrice as good a workman as B and takes 10 days less to do a piece of work than B takes. The number of days taken by B to finish the work is :
View SolutionA can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be
View SolutionA is thrice as efficient as B. Working together they complete the work in 3 days. If B takes 8 days more than A, what is the number of days taken by A to finish the whole work, alone ?
View Solution