Doubtnut Promotions Sticky

A certain number of men can complete a book in 10 days. If there were three more men, then book could be completed in 2 days less. How many men were there in the beginning?

A

a. 8

B

b. 15

C

c. 12

D

d. 10

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, let's denote the number of men initially as x.

Step 1: Understand the total work done
The total work can be calculated as:
Total Work=Number of Men×Number of Days
In the first scenario, x men complete the book in 10 days. Therefore, the total work done can be expressed as:
Total Work=x×10

Step 2: Set up the equation for the second scenario
In the second scenario, if there are 3 more men, the total number of men becomes x+3, and they can complete the book in 8 days (since it is 2 days less than 10 days). Thus, the total work in this case can be expressed as:
Total Work=(x+3)×8

Step 3: Equate the total work from both scenarios
Since the total work remains the same in both scenarios, we can set the two expressions equal to each other:
x×10=(x+3)×8

Step 4: Expand and simplify the equation
Expanding the right side of the equation:
10x=8x+24

Step 5: Rearrange the equation
Now, we can rearrange the equation to isolate x:
10x8x=24
2x=24

Step 6: Solve for x
Now, divide both sides by 2 to find x:
x=242=12

Conclusion
Thus, the number of men in the beginning was 12.

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A certain number of men can complete a job in 30 days. If there were 5 men more, it could be completed in 10 days less. How many men were in the beginning?

    A10
    B15
    C20
    D25
  • Question 2 - Select One

    A certain number of men complete a work in 45 days. If there were 5 men more, the work could be fin- ished in 9 days less How many men were originally there?

    A30
    B15
    C25
    D20
  • Question 3 - Select One

    A certain number of men com plete a piece of work in 60 days. If there were 8 men more, the work can be finished in 10 days less. The number of men originally is:

    A30
    B40
    C32
    D36