A certain number of men can complete a book in 10 days. If there were three more men, then book could be completed in 2 days less. How many men were there in the beginning?
a. 8
b. 15
c. 12
d. 10
The correct Answer is:C
To solve the problem step by step, let's denote the number of men initially as x.
Step 1: Understand the total work done
The total work can be calculated as:
Total Work=Number of Men×Number of Days
In the first scenario, x men complete the book in 10 days. Therefore, the total work done can be expressed as:
Total Work=x×10
Step 2: Set up the equation for the second scenario
In the second scenario, if there are 3 more men, the total number of men becomes x+3, and they can complete the book in 8 days (since it is 2 days less than 10 days). Thus, the total work in this case can be expressed as:
Total Work=(x+3)×8
Step 3: Equate the total work from both scenarios
Since the total work remains the same in both scenarios, we can set the two expressions equal to each other:
x×10=(x+3)×8
Step 4: Expand and simplify the equation
Expanding the right side of the equation:
10x=8x+24
Step 5: Rearrange the equation
Now, we can rearrange the equation to isolate x:
10x−8x=24
2x=24
Step 6: Solve for x
Now, divide both sides by 2 to find x:
x=242=12
Conclusion
Thus, the number of men in the beginning was 12.
The total work can be calculated as:
Total Work=Number of Men×Number of Days
In the first scenario, x men complete the book in 10 days. Therefore, the total work done can be expressed as:
Total Work=x×10
In the second scenario, if there are 3 more men, the total number of men becomes x+3, and they can complete the book in 8 days (since it is 2 days less than 10 days). Thus, the total work in this case can be expressed as:
Total Work=(x+3)×8
Since the total work remains the same in both scenarios, we can set the two expressions equal to each other:
x×10=(x+3)×8
Expanding the right side of the equation:
10x=8x+24
Now, we can rearrange the equation to isolate x:
10x−8x=24
2x=24
Now, divide both sides by 2 to find x:
x=242=12
Thus, the number of men in the beginning was 12.
Similar Questions
A certain number of men can do a work in 60 days. If there were 8 men more it could be finished in 10 days less. How many men are there?
View SolutionA certain number of men completed a job in 10 days. If there 5 more men, it could have been completd in 8 days. How many men will be required to complete it ?
View Solution
Knowledge Check
A certain number of men can complete a job in 30 days. If there were 5 men more, it could be completed in 10 days less. How many men were in the beginning?
A10B15C20D25A certain number of men complete a work in 45 days. If there were 5 men more, the work could be fin- ished in 9 days less How many men were originally there?
A30B15C25D20A certain number of men com plete a piece of work in 60 days. If there were 8 men more, the work can be finished in 10 days less. The number of men originally is:
A30B40C32D36
A certain number of men can do a work in 40 days. If there were 8 men more, it could be finished in 10 days less. How many men were there initially ?
View SolutionA certain number of men can do a piece of work in 80 days. If there were 10 men less, It could be finished in 20 days more. How many men are there in the starting?
View SolutionA certain number of men can do a work in 60 days. If there were 8 men more it could be finished in 10 days less. How many men are there?
View SolutionA certain number of men can do a work in 35 days. If there were 10 men more it could be finished in 10 days less. How many men are there?
View SolutionA certain number of men can do a work in 60 days. If there were 8 men less it could be finished in 10 days more. How many men are there?
View Solution