A certain number of men can do a work in 60 days. If there were 8 men more it could be finished in 10 days less. How many men are there?
50
40
56
58
The correct Answer is:40
To solve the problem step by step, we will follow these steps:
Step 1: Define the Variables
Let the number of men be X.
Step 2: Set Up the Work Equation
According to the problem, X men can complete the work in 60 days. Therefore, the total work can be expressed as:
Total Work=X×60
Step 3: Consider the New Scenario
If there are 8 more men, the new number of men becomes X+8. The work can then be completed in 10 days less, which means it can be done in 60−10=50 days. Thus, the total work can also be expressed as:
Total Work=(X+8)×50
Step 4: Set the Two Expressions for Total Work Equal
Since both expressions represent the same total work, we can set them equal to each other:
X×60=(X+8)×50
Step 5: Expand the Equation
Expanding the right side gives:
60X=50X+400
Step 6: Solve for X
Now, we will isolate X:
60X−50X=400
10X=400
X=40
Step 7: Conclusion
Therefore, the number of men is 40.
Let the number of men be X.
According to the problem, X men can complete the work in 60 days. Therefore, the total work can be expressed as:
Total Work=X×60
If there are 8 more men, the new number of men becomes X+8. The work can then be completed in 10 days less, which means it can be done in 60−10=50 days. Thus, the total work can also be expressed as:
Total Work=(X+8)×50
Since both expressions represent the same total work, we can set them equal to each other:
X×60=(X+8)×50
Expanding the right side gives:
60X=50X+400
Now, we will isolate X:
60X−50X=400
10X=400
X=40
Therefore, the number of men is 40.
Topper's Solved these Questions
Similar Questions
A certain number of men can do a work in 60 days. If there were 8 men more it could be finished in 10 days less. How many men are there?
View SolutionA certain number of men can do a piece of work in 80 days. If there were 10 men less, It could be finished in 20 days more. How many men are there in the starting?
View Solution
Knowledge Check
A certain number of men can do a work in 35 days. If there were 10 men more it could be finished in 10 days less. How many men are there?
A20B25C30D32A certain number of men can do a work in 40 days. If there were 8 men more, it could be finished in 10 days less. How many men were there initially ?
A20B24C30D16A certain number of men can do a work in 60 days. If there were 8 men less it could be finished in 10 days more. How many men are there?
A50B52C56D64
A certain number of men complete a work in 45 days. If there were 5 men more, the work could be fin- ished in 9 days less How many men were originally there?
View SolutionA certain number of men can complete a job in 30 days. If there were 5 men more, it could be completed in 10 days less. How many men were in the beginning?
View SolutionA certain number of men com plete a piece of work in 60 days. If there were 8 men more, the work can be finished in 10 days less. The number of men originally is:
View SolutionA certain number of men com plete a piece of work in 60 days. If there were 8 men more, the work can be finished in 10 days less. The number of men originally is:
View SolutionA certain number of men can do a plece of work in 60 days. If there were 6 men more, the work can be finished 20 days earlier. The number of men working is :
View Solution