Sumit is 28% less efficient than Amit. If Amit can make a wall in 54 days, then Sumit can complete the same work in how many days?
75
70
72
76
The correct Answer is:A
To solve the problem, we need to determine how many days Sumit will take to complete the same work that Amit can do in 54 days, given that Sumit is 28% less efficient than Amit.
1. Understanding Efficiency:
- Let Amit's efficiency be represented as 100% (or a value of 25 units of work per day for easier calculation).
- Since Sumit is 28% less efficient than Amit, we can calculate Sumit’s efficiency:
Sumit's efficiency=100%−28%=72%
- In terms of work units, if Amit's efficiency is 25 units, then Sumit's efficiency is:
Sumit's efficiency=72% of 25=72100×25=18 units per day
2. Calculating Total Work:
- Amit can complete the wall in 54 days. Therefore, the total work can be calculated as:
Total Work=Amit's efficiency×Days taken by Amit=25 units/day×54 days=1350 units
3. Calculating Time Taken by Sumit:
- Now, we need to find out how many days Sumit will take to complete the same total work of 1350 units with his efficiency of 18 units per day:
Days taken by Sumit=Total WorkSumit's efficiency=1350 units18 units/day=75 days
Final Answer:
Sumit can complete the work in 75 days.
- Let Amit's efficiency be represented as 100% (or a value of 25 units of work per day for easier calculation).
- Since Sumit is 28% less efficient than Amit, we can calculate Sumit’s efficiency:
Sumit's efficiency=100%−28%=72%
- In terms of work units, if Amit's efficiency is 25 units, then Sumit's efficiency is:
Sumit's efficiency=72% of 25=72100×25=18 units per day
- Amit can complete the wall in 54 days. Therefore, the total work can be calculated as:
Total Work=Amit's efficiency×Days taken by Amit=25 units/day×54 days=1350 units
- Now, we need to find out how many days Sumit will take to complete the same total work of 1350 units with his efficiency of 18 units per day:
Days taken by Sumit=Total WorkSumit's efficiency=1350 units18 units/day=75 days
Sumit can complete the work in 75 days.
Similar Questions
A is 40 % more efficient than B and B is 20 % less efficient than C. If A takes 6 days less than C to complete a work, then in how many days will B complete this work ?
View SolutionA is 20% more efficient than B.B can do a piece of work in 20 days. In how many days can A do the same work?
View Solution
Knowledge Check
- Question 1 - Select One
Raman is 25% more efficient than Aman. If Aman can complete a piece of work in 25 days, then Raman can complete the same work in how many days?
A12B15C16D20 - Question 2 - Select One
10 men can make a wall in 8 days. How many men required to complete the same work in half day
A80B100C120D160 - Question 3 - Select One
Vijay is 10% more efficient than Vikas. If Vikas can complete a piece of work in 33 days. Then Vijay can complete the same work in how many days ?
A25B27C30D36
Shivam is 10% less efficient than Vivek. If Vivek can make a helmet in 9 days, then in how many days Shivam can complete the same work?
View SolutionA is 20% more efficient than B. If B alone can complete a piece of work in 12 days, then A alone can complete the same work in how many days?
View SolutionA is 20% more efficient than B.B can do a piece of work in 20 days. In how many days can A do the same work?
View SolutionIf 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?
View SolutionP, Q and R together can complete a work in 40 days. P and Q together can complete the same work in 90 days. Then R alone can complete the same work in how many days?
View Solution