10 men can make a wall in 8 days. How many men required to complete the same work in half day
80
100
120
160
The correct Answer is:D
To solve the problem step by step, we can follow this approach:
Step 1: Understand the given information
We know that 10 men can complete the work of making a wall in 8 days.
Step 2: Calculate the total work in man-days
Total work can be calculated as:
Total Work=Number of Men×Number of Days=10 men×8 days=80 man-days
Step 3: Determine the time frame for the new scenario
We need to find out how many men are required to complete the same work (80 man-days) in half a day.
Step 4: Set up the equation for the new scenario
Let x be the number of men required to complete the work in half a day. The total work done by x men in half a day can be expressed as:
Work=x men×0.5 days=0.5x man-days
Step 5: Equate the total work from both scenarios
Since the total work remains the same, we can set up the equation:
80 man-days=0.5x man-days
Step 6: Solve for x
To find x, we can rearrange the equation:
0.5x=80
x=800.5=80×2=160
Conclusion
Thus, the number of men required to complete the work in half a day is 160.
---
We know that 10 men can complete the work of making a wall in 8 days.
Total work can be calculated as:
Total Work=Number of Men×Number of Days=10 men×8 days=80 man-days
We need to find out how many men are required to complete the same work (80 man-days) in half a day.
Let x be the number of men required to complete the work in half a day. The total work done by x men in half a day can be expressed as:
Work=x men×0.5 days=0.5x man-days
Since the total work remains the same, we can set up the equation:
80 man-days=0.5x man-days
To find x, we can rearrange the equation:
0.5x=80
x=800.5=80×2=160
Thus, the number of men required to complete the work in half a day is 160.
Topper's Solved these Questions
- WORK AND TIME BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE HIGHER SKILL LEVEL QUESTION
16 Videos
- WORK AND TIME BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE HIGHER SKILL LEVEL QUESTION
16 Videos
- VOLUME AND SURFACE AREA BOOK - ARIHANT SSCCHAPTER - VOLUME AND SURFACE AREA EXERCISE - FAST TRACK PRACTICE
111 Videos
- WORK AND WAGES BOOK - ARIHANT SSCCHAPTER - WORK AND WAGES EXERCISE - EXERCISE (HIGHER SKILL LEVEL QUESTIONS)
7 Videos
Similar Questions
Knowledge Check
If 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?
A21B20C24D22If 15 men can do a work in 48 days, then how many men will be required to complete the work in 30 days ?
A,21B20C24D22Twelve men can do a piece of work in 15 days. How many men are required to complete a work which is three and a half times the original work in 10 days ?
A18B54C63D70
Twelve men are required to complete a work in 24 days.How many men are required to complete twice the work in 16 days?
View SolutionTwelve men can do a piece of work in 15 days. How many men are required to complete a work which is three and a half times the original work in 10 days ?
View SolutionTwelve men can do a piece of work in 15 days. How many men are required to complete a work which is three and a half times the original work in 10 days ?
View Solution10 men can finish the construction of a wall in 8 days.How many men are added to finish the work in half a day ?
View Solution15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
View Solution