10 men can make a wall in 8 days. How many men required to complete the same work in half day

A

80

B

100

C

120

D

160

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we can follow this approach:

Step 1: Understand the given information
We know that 10 men can complete the work of making a wall in 8 days.

Step 2: Calculate the total work in man-days
Total work can be calculated as:
Total Work=Number of Men×Number of Days=10 men×8 days=80 man-days

Step 3: Determine the time frame for the new scenario
We need to find out how many men are required to complete the same work (80 man-days) in half a day.

Step 4: Set up the equation for the new scenario
Let x be the number of men required to complete the work in half a day. The total work done by x men in half a day can be expressed as:
Work=x men×0.5 days=0.5x man-days

Step 5: Equate the total work from both scenarios
Since the total work remains the same, we can set up the equation:
80 man-days=0.5x man-days

Step 6: Solve for x
To find x, we can rearrange the equation:
0.5x=80
x=800.5=80×2=160

Conclusion
Thus, the number of men required to complete the work in half a day is 160.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • If 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?

    A21
    B20
    C24
    D22
  • If 15 men can do a work in 48 days, then how many men will be required to complete the work in 30 days ?

    A,21
    B20
    C24
    D22
  • Twelve men can do a piece of work in 15 days. How many men are required to complete a work which is three and a half times the original work in 10 days ?

    A18
    B54
    C63
    D70