There were many works that I had to do.
There was a lot of work that I had to do.
Similar Questions
Change the following into indirect speech
Ram said, "I had to do the work."
View SolutionA can do a piece of work in 14 days while B can do it in 21 days. They began together and worked at it for 6 days. Then A fell ill and B had to complete the remaining work alone. In how many days was the work completed?
View Solution
Knowledge Check
My family is my priority but there were times when I had to ______ because of work pressures.
Alook infoBsit inCpull awayDput offFill in the blank with correct option
My family is my priority but there were times when I had to ______ because of work pressures.Ai) look intoBii) sit inCiii) pull awayDiv) put offA contractor undertook a work to complete in 60 days. But just after 20 days he observed that only 15th of the project work had been completed. To complete the work in time in rest days minimum how many workers he had to increase, if there were initially 75 workers were deployed for the task?
A25B50C75Dcan't be determined
A certain numner of men agreed to do a work in 20 days. 5 men did come for work. Others completed the work in 40 days. Find the number of men who had agreed to do the work originally.
View SolutionOn my return from a long holiday, I had to ...... with a lot of work.
View SolutionFind out which part of a sentence has an error
View SolutionA can finish a work in 12 days and B can do it in 15 days. ’After A had worked for 3 days, B also joined A to finish the remaining work. In how many days, the remaining work will be finished?
View SolutionA can finish a work in 12 days and B can do it in 15 days. After A had worked for 3 days, B also joined A to finish the remaining work. In how many days, the remaining work will be finished?
View Solution