A certain numner of men agreed to do a work in 20 days. 5 men did come for work. Others completed the work in 40 days. Find the number of men who had agreed to do the work originally.
A) 8
B) 10
C) 12
D) 15
The correct Answer is:B
To solve the problem, we need to determine the original number of men who agreed to complete the work in 20 days. Let's break it down step by step.
Step 1: Define Variables
Let x be the original number of men who agreed to do the work.
Step 2: Calculate Work Done
The total work can be expressed in terms of man-days. If x men can complete the work in 20 days, the total work W is:
W=x×20
Step 3: Determine Remaining Men
Since 5 men did not come for work, the number of men who actually worked is:
x−5
Step 4: Calculate Work Done by Remaining Men
These remaining men completed the work in 40 days. Therefore, the work done by these men can be expressed as:
W=(x−5)×40
Step 5: Set Up the Equation
Since the total work W is the same in both scenarios, we can set the two equations equal to each other:
x×20=(x−5)×40
Step 6: Expand and Simplify the Equation
Expanding the right side gives:
20x=40x−200
Step 7: Rearrange the Equation
Rearranging the equation to isolate x:
20x−40x=−200
−20x=−200
20x=200
Step 8: Solve for x
Dividing both sides by 20 gives:
x=10
Conclusion
The original number of men who had agreed to do the work is 10.
---
Let x be the original number of men who agreed to do the work.
The total work can be expressed in terms of man-days. If x men can complete the work in 20 days, the total work W is:
W=x×20
Since 5 men did not come for work, the number of men who actually worked is:
x−5
These remaining men completed the work in 40 days. Therefore, the work done by these men can be expressed as:
W=(x−5)×40
Since the total work W is the same in both scenarios, we can set the two equations equal to each other:
x×20=(x−5)×40
Expanding the right side gives:
20x=40x−200
Rearranging the equation to isolate x:
20x−40x=−200
−20x=−200
20x=200
Dividing both sides by 20 gives:
x=10
The original number of men who had agreed to do the work is 10.
Similar Questions
Knowledge Check
- Question 1 - Select One
24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
A32 menB30 menC35 menD36 men - Question 2 - Select One
If 15 men can do a work in 48 days, then how many men will be required to complete the work in 30 days ?
A,21B20C24D22 - Question 3 - Select One
A certain number of men can do a plece of work in 60 days. If there were 6 men more, the work can be finished 20 days earlier. The number of men working is :
A6B12C18D24
A certain number of men can do a piece of work in 40 days. If there were 45 men more the work could have been finished in 25 days. Find the original number of men employed in the work (A) 70 (B) 85 (C) 65 (D) 75
View Solution12 men of 15 women can do a work in 40 days. 8 men and 10 women can do the work in how many days?
View SolutionA group of men decided to do a work in 10 days, but 5 of them become absent. if the rest of the group did the work in 12 days, find the original number of men?
View SolutionIf 10 men can do a work in 20 days, then how many men can do the same work in 4 days?
(a)60 men
(b)20 men
(c)50 men
(d)40 menView SolutionA certain number of men can do a work in 60 days. If there were 8 men more it could be finished in 10 days less. How many men are there?
View Solution