Doubtnut Promotions Sticky

A certain numner of men agreed to do a work in 20 days. 5 men did come for work. Others completed the work in 40 days. Find the number of men who had agreed to do the work originally.

A

A) 8

B

B) 10

C

C) 12

D

D) 15

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem, we need to determine the original number of men who agreed to complete the work in 20 days. Let's break it down step by step.

Step 1: Define Variables
Let x be the original number of men who agreed to do the work.

Step 2: Calculate Work Done
The total work can be expressed in terms of man-days. If x men can complete the work in 20 days, the total work W is:
W=x×20

Step 3: Determine Remaining Men
Since 5 men did not come for work, the number of men who actually worked is:
x5

Step 4: Calculate Work Done by Remaining Men
These remaining men completed the work in 40 days. Therefore, the work done by these men can be expressed as:
W=(x5)×40

Step 5: Set Up the Equation
Since the total work W is the same in both scenarios, we can set the two equations equal to each other:
x×20=(x5)×40

Step 6: Expand and Simplify the Equation
Expanding the right side gives:
20x=40x200

Step 7: Rearrange the Equation
Rearranging the equation to isolate x:
20x40x=200
20x=200
20x=200

Step 8: Solve for x
Dividing both sides by 20 gives:
x=10

Conclusion
The original number of men who had agreed to do the work is 10.

---

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :

    A32 men
    B30 men
    C35 men
    D36 men
  • Question 2 - Select One

    If 15 men can do a work in 48 days, then how many men will be required to complete the work in 30 days ?

    A,21
    B20
    C24
    D22
  • Question 3 - Select One

    A certain number of men can do a plece of work in 60 days. If there were 6 men more, the work can be finished 20 days earlier. The number of men working is :

    A6
    B12
    C18
    D24