Manish is four times as efficient as Puneet. Manish takes 90 days less than Puneet to complete a book. If both of them work together, then in how many days the book will be completed?

A

28

B

25

C

24

D

30

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we can follow these steps:

Step 1: Define the efficiencies
Let Puneet's efficiency be E. Since Manish is four times as efficient as Puneet, Manish's efficiency will be 4E.

Step 2: Define the time taken to complete the book
Let Puneet take D days to complete the book. Therefore, Manish will take D90 days to complete the same book.

Step 3: Relate efficiency to time
The relationship between efficiency and time is given by:
Efficiency=Total WorkTime Taken
Since both are completing the same work (let's assume the total work is 1 book), we can express their efficiencies in terms of days:
- For Puneet:
E=1D
- For Manish:
4E=1D90

Step 4: Set up the equation
From the efficiencies, we can set up the equation:
4(1D)=1D90
Multiplying both sides by D(D90) to eliminate the denominators gives:
4(D90)=D

Step 5: Solve for D
Expanding the equation:
4D360=D
Rearranging gives:
4DD=360
3D=360
D=120

Step 6: Calculate Manish's time
Now that we have D, we can find the time taken by Manish:
Time taken by Manish=D90=12090=30 days

Step 7: Calculate the combined work rate
Now, we can find their combined work rate.
- Manish's work rate is 130 (books per day).
- Puneet's work rate is 1120 (books per day).

The combined work rate when both work together is:
Combined Work Rate=130+1120
To add these fractions, we need a common denominator, which is 120:
130=4120
Thus,
Combined Work Rate=4120+1120=5120=124

Step 8: Calculate the time taken when working together
If their combined work rate is 124, it means together they can complete the book in:
Time=1 book124 books per day=24 days

Final Answer
Thus, the book will be completed in 24 days when both Manish and Puneet work together.

---

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    Mohit is five times more efficient as Rohit. If Mohit can complete a piece of work in 28 days less than Rohit, then in how many days can Rohit alone complete the same work?
    मोहित रोहित से पांच गुना अधिक कार्य कुशल है। अगर मोहित किसी कार्य को पूरा करने में रोहित की तुलना में 28 दिन कम का समय लेता है,तो रोहित अकेले इस कार्य को कितने दिन में पूरा करेगा ?

    A10
    B12.5
    C15
    D20
  • Question 2 - Select One

    P is four times as efficient as Q. P can complete a work in 45 days less than Q. If both of them work together, then in how many days the work will be completed?

    A10
    B12
    C15
    D30
  • Question 3 - Select One

    A is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed?

    A17
    B19
    C19.5
    D21