Manish is four times as efficient as Puneet. Manish takes 90 days less than Puneet to complete a book. If both of them work together, then in how many days the book will be completed?
28
25
24
30
The correct Answer is:C
To solve the problem step by step, we can follow these steps:
Step 1: Define the efficiencies
Let Puneet's efficiency be E. Since Manish is four times as efficient as Puneet, Manish's efficiency will be 4E.
Step 2: Define the time taken to complete the book
Let Puneet take D days to complete the book. Therefore, Manish will take D−90 days to complete the same book.
Step 3: Relate efficiency to time
The relationship between efficiency and time is given by:
Efficiency=Total WorkTime Taken
Since both are completing the same work (let's assume the total work is 1 book), we can express their efficiencies in terms of days:
- For Puneet:
E=1D
- For Manish:
4E=1D−90
Step 4: Set up the equation
From the efficiencies, we can set up the equation:
4(1D)=1D−90
Multiplying both sides by D(D−90) to eliminate the denominators gives:
4(D−90)=D
Step 5: Solve for D
Expanding the equation:
4D−360=D
Rearranging gives:
4D−D=360
3D=360
D=120
Step 6: Calculate Manish's time
Now that we have D, we can find the time taken by Manish:
Time taken by Manish=D−90=120−90=30 days
Step 7: Calculate the combined work rate
Now, we can find their combined work rate.
- Manish's work rate is 130 (books per day).
- Puneet's work rate is 1120 (books per day).
The combined work rate when both work together is:
Combined Work Rate=130+1120
To add these fractions, we need a common denominator, which is 120:
130=4120
Thus,
Combined Work Rate=4120+1120=5120=124
Step 8: Calculate the time taken when working together
If their combined work rate is 124, it means together they can complete the book in:
Time=1 book124 books per day=24 days
Final Answer
Thus, the book will be completed in 24 days when both Manish and Puneet work together.
---
Let Puneet's efficiency be E. Since Manish is four times as efficient as Puneet, Manish's efficiency will be 4E.
Let Puneet take D days to complete the book. Therefore, Manish will take D−90 days to complete the same book.
The relationship between efficiency and time is given by:
Efficiency=Total WorkTime Taken
Since both are completing the same work (let's assume the total work is 1 book), we can express their efficiencies in terms of days:
- For Puneet:
E=1D
- For Manish:
4E=1D−90
From the efficiencies, we can set up the equation:
4(1D)=1D−90
Multiplying both sides by D(D−90) to eliminate the denominators gives:
4(D−90)=D
Expanding the equation:
4D−360=D
Rearranging gives:
4D−D=360
3D=360
D=120
Now that we have D, we can find the time taken by Manish:
Time taken by Manish=D−90=120−90=30 days
Now, we can find their combined work rate.
- Manish's work rate is 130 (books per day).
- Puneet's work rate is 1120 (books per day).
Combined Work Rate=130+1120
To add these fractions, we need a common denominator, which is 120:
130=4120
Thus,
Combined Work Rate=4120+1120=5120=124
If their combined work rate is 124, it means together they can complete the book in:
Time=1 book124 books per day=24 days
Thus, the book will be completed in 24 days when both Manish and Puneet work together.
Similar Questions
A is 40 % more efficient than B and B is 20 % less efficient than C. If A takes 6 days less than C to complete a work, then in how many days will B complete this work ?
View SolutionP is twice as efficient as 0.Q takes 12 days to complete a job. If both of them work together, how much time will they take to complete the job?
(A) 6 days
(B) 4 days
(C) 5 days
(D) 3 daysView Solution
Knowledge Check
- Question 1 - Select One
Mohit is five times more efficient as Rohit. If Mohit can complete a piece of work in 28 days less than Rohit, then in how many days can Rohit alone complete the same work?
मोहित रोहित से पांच गुना अधिक कार्य कुशल है। अगर मोहित किसी कार्य को पूरा करने में रोहित की तुलना में 28 दिन कम का समय लेता है,तो रोहित अकेले इस कार्य को कितने दिन में पूरा करेगा ?A10B12.5C15D20 - Question 2 - Select One
P is four times as efficient as Q. P can complete a work in 45 days less than Q. If both of them work together, then in how many days the work will be completed?
A10B12C15D30 - Question 3 - Select One
A is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed?
A17B19C19.5D21
A is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed?
View SolutionA man completes a job in 15 days. His son completes the same job in 10 days. If both work together then in how many days the work will be completed ?
View SolutionA man completes a work in 12 days another man completes the same work 10 days. If both work together, then how many days will the work completed ?
View SolutionA is three times efficient than B. If A takes 24 days less than B to complete the work, then find in how many days A and B together can complete the whole work.
View SolutionX works four times as fast as Y.Y takes 60 days more than X to complete a job. Find the time in which X and Y working together can complete the job ( in days)
View Solution