Doubtnut Promotions Sticky

A is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed?

A

17

B

19

C

19.5

D

21

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will break it down into manageable parts.

Step 1: Determine the time taken by A and B to complete the work.
Let the time taken by B to complete the work be x days. Since A is 1.5 times more efficient than B, the time taken by A to complete the work will be x1.5=2x3.

According to the problem, A takes 8 days less than B to complete the work:
2x3=x8

Step 2: Solve the equation for x.
To eliminate the fraction, multiply the entire equation by 3:
2x=3x24
Rearranging gives:
3x2x=24x=24

Step 3: Calculate the time taken by A.
Now that we have x=24, we can find the time taken by A:
Time taken by A=2x3=2×243=16 days

Step 4: Determine the work done by A and B in one day.
The work done by A in one day is:
Work done by A in one day=116
The work done by B in one day is:
Work done by B in one day=124

Step 5: Calculate the total work done in two days.
Since A and B work on alternate days, we can calculate the work done in 2 days (A works on the first day and B on the second day):
Work done in 2 days=116+124
To add these fractions, find a common denominator (which is 48):
116=348,124=248
Thus,
Work done in 2 days=348+248=548

Step 6: Calculate the total number of days required to complete the work.
Let W be the total work, which we can consider as 1 unit of work. The number of 2-day cycles needed to complete the work is:
Number of 2-day cycles=1548=485=9.6 cycles
This means it will take 9 complete cycles (18 days) and a fraction of a cycle to complete the work.

Step 7: Calculate the remaining work after 9 cycles.
After 9 cycles (18 days), the work done is:
Work done in 18 days=9×548=4548
The remaining work is:
14548=348=116

Step 8: Determine how long it will take to finish the remaining work.
Since A works on the first day of the next cycle, A will complete the remaining work of 116 in 1 day.

Final Calculation: Total days taken.
Thus, the total days taken to complete the work is:
Total days=18+1=19 days

Conclusion:
The work will be completed in 19 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A is three times efficient than B. If A takes 24 days less than B to complete the work, then find in how many days A and B together can complete the whole work.

    A9 days
    B12 days
    C18 days
    D24 days
  • Question 2 - Select One

    P is four times as efficient as Q. P can complete a work in 45 days less than Q. If both of them work together, then in how many days the work will be completed?

    A10
    B12
    C15
    D30
  • Question 3 - Select One

    A is twice as good a workman as B and therefore A takes 6 days less than B to finish the work individually. If A and B working complete together the work in 4 days, then how many days are required by B to complete the work alone?

    A12
    B18
    C8
    D6