If 60 boys can finish a work in 15 days by working 8 hours a day, then how many hours a day should 72 boys work to finish that work within 20 days?
4
6
5
7
The correct Answer is:C
To solve the problem, we will use the concept of "man-days," which is a way to quantify the amount of work done based on the number of workers, the number of days they work, and the hours they work each day.
1. Identify the given values:
- Number of boys (workers) in the first scenario, m1=60
- Number of days in the first scenario, d1=15
- Number of hours worked per day in the first scenario, h1=8
- Number of boys in the second scenario, m2=72
- Number of days in the second scenario, d2=20
- Number of hours worked per day in the second scenario, h2=? (this is what we need to find)
2. Set up the equation using the man-days formula:
m1×d1×h1=m2×d2×h2
Substituting the known values:
60×15×8=72×20×h2
3. Calculate the left side of the equation:
60×15=900
900×8=7200
So, the left side becomes:
7200=72×20×h2
4. Calculate the right side without h2:
72×20=1440
Thus, we have:
7200=1440×h2
5. Solve for h2:
h2=72001440
h2=5
6. Conclusion:
The number of hours per day that 72 boys should work to finish the work in 20 days is 5 hours.
Final Answer:
5 hours a day
- Number of boys (workers) in the first scenario, m1=60
- Number of days in the first scenario, d1=15
- Number of hours worked per day in the first scenario, h1=8
- Number of boys in the second scenario, m2=72
- Number of days in the second scenario, d2=20
- Number of hours worked per day in the second scenario, h2=? (this is what we need to find)
m1×d1×h1=m2×d2×h2
Substituting the known values:
60×15×8=72×20×h2
60×15=900
900×8=7200
So, the left side becomes:
7200=72×20×h2
72×20=1440
Thus, we have:
7200=1440×h2
h2=72001440
h2=5
The number of hours per day that 72 boys should work to finish the work in 20 days is 5 hours.
5 hours a day
Similar Questions
Working 8 hours a day, Ashu can copy a book in 18 days. How many hours a day should he work so as to finish the work in 12 days?
View Solution30 labourers working 7 hours a day can finish a piece of work in 18 days. If the labourers work 6 hours a day, then the number of labourers to finish the same piece of work in30 days, will be: 15 b. 21 c. 22 d. 25
View Solution
Knowledge Check
- Question 1 - Select One
Working 8 hours a day, Anu can copy a book in 18 days. How many hours a day should she work so as to finish the work in 12 days ?
A12 hoursB10 hoursC11 hoursD13 hours - Question 2 - Select One
24 men working 8 hours a day can finish a work in 10 days. Working at the rate of 10 hours a day, the number of men required to finish the same work in 6 days is:
Aa. 30Bb. 32Cc. 34Dd. 36 - Question 3 - Select One
Working 9 hours a day, Manish can read a book in 16 days. How many hours a day should he work so as to finish the same work in 24 days?
A5B7C8D6
Working 9 hours a day, Manish can read a book in 16 days. How many hours a day should he work so as to finish the same work in 24 days?
View SolutionWorking 5 hours a day, Shivam can read a book in 24 days. How many hours a day should he work so as to finish the same work in 8 days?
View SolutionWorking 10 hours a day, Aman can complete a piece of work in 18 days. How many hours a day should he work so as to finish the work in 15 days ?
View SolutionIf 3 men or 6 boy, can do a piece of work in 10 days, working 7 hours a day; how many days will it take to complete a piece of work twice as large with 6 men and 2 boy. 1% 'irking together for 8 hours a day? 6 b. 9 c. 812 d. 712
View SolutionWorking 15 hours a day, Goldy can complete a piece of work in 24 days. How many hours a day he should work so as to finish the work in 18 days?
View Solution