A can do piece of work in 6 days. B is 25% more than efficient than A. How long would B alone take to finish this work?
days
days
days
days
The correct Answer is:B
To solve the problem, let's break it down step by step.
Step 1: Determine A's Work Rate
A can complete the work in 6 days. Therefore, A's work rate is:
Work rate of A=1 work6 days=16 work per day
Step 2: Calculate B's Work Rate
B is 25% more efficient than A. To find B's work rate, we first need to calculate 25% of A's work rate:
25% of A's work rate=0.25×16=0.256=124
Now, we add this to A's work rate to find B's work rate:
Work rate of B=Work rate of A+25% of A's work rate=16+124
To add these fractions, we need a common denominator. The least common multiple of 6 and 24 is 24:
16=424
Now we can add:
Work rate of B=424+124=524 work per day
Step 3: Calculate the Time Taken by B to Complete the Work
To find out how long B would take to finish the work alone, we take the reciprocal of B's work rate:
Time taken by B=1 workWork rate of B=1524=245 days
This can be simplified to:
245=4.8 days
Final Answer
B alone would take 4.8 days to finish the work.
---
A can complete the work in 6 days. Therefore, A's work rate is:
Work rate of A=1 work6 days=16 work per day
B is 25% more efficient than A. To find B's work rate, we first need to calculate 25% of A's work rate:
25% of A's work rate=0.25×16=0.256=124
Now, we add this to A's work rate to find B's work rate:
Work rate of B=Work rate of A+25% of A's work rate=16+124
To add these fractions, we need a common denominator. The least common multiple of 6 and 24 is 24:
16=424
Now we can add:
Work rate of B=424+124=524 work per day
To find out how long B would take to finish the work alone, we take the reciprocal of B's work rate:
Time taken by B=1 workWork rate of B=1524=245 days
This can be simplified to:
245=4.8 days
B alone would take 4.8 days to finish the work.
Similar Questions
Knowledge Check
- Question 1 - Select One
A can do a piece of work in 6 days. B is 25% more efficient than A. How long would B alone take to finish this work?
A446 daysB313 daysC514 daysD223 days - Question 2 - Select One
A can do a piece of work in 15 days. B is 50% more efficient than A, B can finish it in
A10daysB712 daysC12daysD1012 days - Question 3 - Select One
A can do a piece of work in 24 days. If B is 60% more efficient than A, then how many days does B require to do the same work?
A17 daysB18 daysC15 daysD12 days
A can do a picec of work in 10 days and B is 25% more
efficient than A. In what time will the work be finished if A
and B work together ?View SolutionA can do a piece of work in 24 days. If B is 50% more efficient than A, then in how many days can B do the same work?
View SolutionA can do a piece of work in 48 days. If B is 50% more efficient than A, then in how many days can B do the same work?
View SolutionA can do a certain job in 12 days. B in 60% more efficient than A. What is the number of days it takes B to do the same piece of work ?
View SolutionA can complete a piece of work in 12 days. B is 60% more efficient than A. The number of days, that B will take to complete the same work, is
View Solution