Doubtnut Promotions Sticky

A, B and C can do a piece of work in 20, 40 and 80 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?

A

7 days

B

15 days

C

18 days

D

16 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem, we need to determine how many days A can complete the work if he is assisted by B and C on every third day. Let's break it down step by step.

Step 1: Determine the work rates of A, B, and C
- A can complete the work in 20 days, so his work rate is:
Work rate of A=120 (work per day)
- B can complete the work in 40 days, so his work rate is:
Work rate of B=140 (work per day)
- C can complete the work in 80 days, so his work rate is:
Work rate of C=180 (work per day)

Step 2: Calculate the combined work rate of A, B, and C
On the third day, A is assisted by B and C. Therefore, the combined work rate of A, B, and C is:
Combined work rate=Work rate of A+Work rate of B+Work rate of C
Calculating this:
Combined work rate=120+140+180
To add these fractions, we need a common denominator. The least common multiple of 20, 40, and 80 is 80:
Combined work rate=480+280+180=780

Step 3: Calculate the work done in a cycle of 3 days
In the first two days, only A works:
Work done by A in 2 days=2×120=220=110
On the third day, A, B, and C work together:
Work done by A, B, and C on the 3rd day=780
Thus, the total work done in 3 days is:
Total work in 3 days=110+780
Converting 110 to a fraction with a denominator of 80:
110=880
So,
Total work in 3 days=880+780=1580=316

Step 4: Determine how many cycles are needed to complete the work
To complete 1 unit of work, we can find out how many cycles of 3 days are needed:
Number of cycles=1316=1635.33 cycles
This means it takes 5 complete cycles (15 days) and a portion of the next cycle.

Step 5: Calculate the work done in 15 days
In 15 days, the total work done is:
Total work done in 15 days=5×316=1516

Step 6: Determine the remaining work
The remaining work after 15 days is:
Remaining work=11516=116

Step 7: Calculate the work done on the 16th and 17th days
On the 16th and 17th days, A works alone:
- Work done by A in 2 days:
Work done by A in 2 days=2×120=220=110
Now, we need to check if the remaining work can be completed in these 2 days:
- Convert 110 to a fraction with a denominator of 16:
110=1.616
Since 1.616>116, A can complete the remaining work on the 17th day.

Conclusion
Thus, the total time taken to complete the work is:
15 days+1 day=16 days

Final Answer
A can complete the work in 16 days.

---

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?

    A10 days
    B12 days
    C15 days
    D20 days
  • Question 2 - Select One

    A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day? 12 days b. 15 days c. 16 days d. 18 days

    A12 days
    B15 days
    C16 days
    D18 days
  • Question 3 - Select One

    A, B and C can do piece ofwork in 30 days, 45 days and 90 days, respectively. A starts the work and heis assisted by B and C togetheron every third day. In how many dayswill the work be completed?

    A23
    B24
    C2212
    D30