A, B and C can do a piece of work in 12, 15 and 20 days respectively. In how many days will all three do this work together ?
The correct Answer is:5 days
To solve the problem, we will follow these steps:
Step 1: Determine the individual work rates of A, B, and C.
- A can complete the work in 12 days, so A's work rate is 112 of the work per day.
- B can complete the work in 15 days, so B's work rate is 115 of the work per day.
- C can complete the work in 20 days, so C's work rate is 120 of the work per day.
Step 2: Find a common work unit.
To make calculations easier, we can assume the total work is the least common multiple (LCM) of the days taken by A, B, and C.
- The LCM of 12, 15, and 20 is 60 units.
Step 3: Calculate the individual work done per day.
- A's work per day:
Work by A=60 units12 days=5 units/day
- B's work per day:
Work by B=60 units15 days=4 units/day
- C's work per day:
Work by C=60 units20 days=3 units/day
Step 4: Calculate the total work done per day when A, B, and C work together.
- Total work done per day by A, B, and C:
Total work per day=5+4+3=12 units/day
Step 5: Calculate the total time taken to complete the work together.
- Using the formula:
Number of days=Total workTotal work per day=60 units12 units/day=5 days
Final Answer:
A, B, and C together will complete the work in 5 days.
---
- A can complete the work in 12 days, so A's work rate is 112 of the work per day.
- B can complete the work in 15 days, so B's work rate is 115 of the work per day.
- C can complete the work in 20 days, so C's work rate is 120 of the work per day.
To make calculations easier, we can assume the total work is the least common multiple (LCM) of the days taken by A, B, and C.
- The LCM of 12, 15, and 20 is 60 units.
- A's work per day:
Work by A=60 units12 days=5 units/day
- B's work per day:
Work by B=60 units15 days=4 units/day
- C's work per day:
Work by C=60 units20 days=3 units/day
- Total work done per day by A, B, and C:
Total work per day=5+4+3=12 units/day
- Using the formula:
Number of days=Total workTotal work per day=60 units12 units/day=5 days
A, B, and C together will complete the work in 5 days.
Topper's Solved these Questions
Similar Questions
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day? a. 12 days b. 15 days c. 16 days d. 18 days
View SolutionA can do a piece of work in 30 days and B can do same work in 60 days. In how many days will A & B do this work together ?
View Solution
Knowledge Check
- Question 1 - Select One
If A, B, and C can do a piece of work in 15, 30, and 60 days respectively. In how many days together they will do the same work?
A10 daysB12 daysC60/11 daysD60/7 days - Question 2 - Select One
A, B and C, one can do a piece of work in 9, 12 and 18 days respectively. They all started the work together, but A left after 3 days. In how many days, was the remaining work completed?
A2B52C114D95 - Question 3 - Select One
A, B and C can do a piece of work in 10 days, 12 days and 15 days respectively. How long will they take to finish it if they work together?
A2daysB3daysC5daysD4days
A,B andC can do a job working alone in 12, 16 and 24 days, respectively.In how many days, they can do the job, if they worked together?
View SolutionA, B and C can do a piece of work in 15, 12 and 20 days respectively. They started the work together, but C left after 2 days. In how many days will the remaining work be completed by A and B?
View SolutionA and B can do a piece of work in 15 days,B and C in 12 days, C and A in 20 days . How many days will be taken by A, B and C working together to finish the work?
View Solution(A + B) can do a piece of work in 20 days and A can do same work in 60 days. In how many days will B do this work ?
View SolutionA and B can do piece of work in 12 days; B and C in 15 days; C and A in 20 days. In how many days will they finish it together and separately ?
View Solution