A and B can together complete a task 40 days. They worked together for 30 days and then left. A finished the remaining task in next 22 days. In how many days A alone can finish the task?
A
48 days
B
88 days
C
30 days
D
40 days
Video Solution
Text Solution
The correct Answer is:B
|
Answer
Step by step video, text & image solution for A and B can together complete a task 40 days. They worked together for 30 days and then left. A finished the remaining task in next 22 days. In how many days A alone can finish the task? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Updated on:21/07/2023
Knowledge Check
- Question 1 - Select One
A and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?
A60B50C40D30 - Question 1 - Select One
A and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 20 days. A finished the remaining work. In how many days A alone can finish the job?
A50 daysB60 daysC48 daysD54 days - Question 1 - Select One
A and B can together finish a work in 30 days. They worked for it for 20 days and then B left. The remaining work was done by A alone in 20 more days. A alone can finish the work in…
A48 daysB50 daysC54 daysD60 days - Question 1 - Select One
A can do a piece of work in 20 days and B in 30 days. They work together for 7 days and then both leave the work. Then Calone finIshes the remaining work in 10 days. In how many days will finish the full work?
A25 daysB30 daysC24 daysD20 days - Question 1 - Select One
Arjun started a task and left it after working for 2 days. Then, Bharath was called and he completed the task in 9 days. If Arjun alone had worked for 3 days, Bharath alone would have finished the remaining work in 6 days. In how many days can Arjun alone complete the task?
A8 daysB12 daysC5 daysD10 days - Question 1 - Select One
A and B complete a work in 16 days, while A alone can finish that work in 24 days. In how many days, B alone can finish that work ?
A56 daysB48 daysC36 daysD64 days - Question 1 - Select One
A can do a piece of work in 30 days and B can do the same piece of work in 20 days. They start working together and work for 4 days and then both leave the work. C alone finishes the remaining work in 18 days. In how many days will C alone finish the whole work?
A30B27C25D24 - Question 1 - Select One or More
A can do a piece of work in 20 days and B can do the same piece of work in 30 days. They start working together and work for 5 days and then both leave he work. C alone finishes the remaining work in 14 days. In how many days will C alone finish the whole work?
A24B18C36D42 - Question 1 - Select One
A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
A60 daysB36 daysC45 daysD24 days