A and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 20 days. A finished the remaining work. In how many days A alone can finish the job?
50 days
60 days
48 days
54 days
The correct Answer is:B
To solve the problem, we will follow these steps:
Step 1: Determine the work done by A and B together in one day.
Since A and B can finish the work together in 30 days, the amount of work they complete in one day is:
Work done by A and B in one day=130
Step 2: Calculate the work done by A and B in 20 days.
In 20 days, the work done by A and B together is:
Work done in 20 days=20×130=2030=23
Step 3: Determine the remaining work after 20 days.
The total work is considered as 1 (or 100%). After A and B have worked together for 20 days, the remaining work is:
Remaining work=1−23=13
Step 4: Calculate the work done by A in the next 20 days.
After B leaves, A finishes the remaining work in 20 days. Therefore, the rate at which A works can be calculated as follows:
Let A's work rate be a (work done by A in one day). In 20 days, A completes the remaining work of 13:
20a=13
From this, we can solve for a:
a=13÷20=160
Step 5: Determine how long A alone would take to finish the job.
Since A can complete 160 of the work in one day, the total time taken by A to finish the entire work (1 unit of work) is:
Time taken by A alone=1a=1160=60 days
Final Answer:
A alone can finish the job in 60 days.
---
Since A and B can finish the work together in 30 days, the amount of work they complete in one day is:
Work done by A and B in one day=130
In 20 days, the work done by A and B together is:
Work done in 20 days=20×130=2030=23
The total work is considered as 1 (or 100%). After A and B have worked together for 20 days, the remaining work is:
Remaining work=1−23=13
After B leaves, A finishes the remaining work in 20 days. Therefore, the rate at which A works can be calculated as follows:
Let A's work rate be a (work done by A in one day). In 20 days, A completes the remaining work of 13:
20a=13
From this, we can solve for a:
a=13÷20=160
Since A can complete 160 of the work in one day, the total time taken by A to finish the entire work (1 unit of work) is:
Time taken by A alone=1a=1160=60 days
A alone can finish the job in 60 days.
Topper's Solved these Questions
- TIME AND WORKBOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-III
31 Videos
- TIME AND WORKBOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-IV
32 Videos
- TIME AND WORKBOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TEST YOURSELF
25 Videos
- TIME AND DISTANCEBOOK - KIRAN PUBLICATIONCHAPTER - TIME AND DISTANCEEXERCISE - Type -XI
74 Videos
- TRIGONOMETRY BOOK - KIRAN PUBLICATIONCHAPTER - TRIGONOMETRY EXERCISE - TEST YOURSELF
25 Videos
Similar Questions
A and B do a piece of work in 20 days and B in 15 days. They work together for 2 days and then A goes away. In how many days will B finish the remaining work?
View SolutionA and B can together finish a work in 30 days. They worked for it for 20 days and then B left. The remaining work was done by A alone in 20 more days. A alone can finish the work in…
View Solution
Knowledge Check
A and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?
A60B50C40D30S and T can finish a work in 50 days. They worked together for 20 days and then left . How much of the work is left
A3/5B1/3C1/2D2/5A and B can together complete a task 40 days. They worked together for 30 days and then left. A finished the remaining task in next 22 days. In how many days A alone can finish the task?
A48 daysB88 daysC30 daysD40 days
A can do a piece of work in 12 days and B in 15 days. They work together for 5 days and then B left. The days taken by A to finish the remaining work is
View SolutionA can do a piece of work in 20 days and B in 30 days. They work together for 7 days and then both leave the work. Then Calone finIshes the remaining work in 10 days. In how many days will finish the full work?
View SolutionA can do a piece of work in 30 days and B can do the same piece of work in 20 days. They start working together and work for 4 days and then both leave the work. C alone finishes the remaining work in 18 days. In how many days will C alone finish the whole work?
View SolutionA can do a piece of work in 20 days and B can do the same piece of work in 30 days. They start working together and work for 5 days and then both leave he work. C alone finishes the remaining work in 14 days. In how many days will C alone finish the whole work?
View SolutionP can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?
View Solution