Doubtnut Promotions Sticky

If C alone can complete two-third part of a work in 12 days, then in how many days C can complete the whole work?

A

24 days

B

15 days

C

8 days

D

18 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will use the information given about C's work rate.

Step 1: Understand the given information
C can complete two-thirds (2/3) of the work in 12 days.

Step 2: Determine the time taken to complete the whole work
We need to find out how many days C would take to complete the entire work (1 whole work).

Step 3: Use the formula for work completion
The formula to find the time taken to complete the whole work when a person can complete a fraction of the work in a certain number of days is:

Total time=Days taken×Total workPart of work completed

In this case:
- Days taken = 12 days
- Part of work completed = 2/3
- Total work = 1 (whole work)

Step 4: Substitute the values into the formula
We can substitute the values into the formula:

Total time=12×123

Step 5: Simplify the expression
To simplify 123, we can multiply by the reciprocal:

123=32

Now substituting this back into the equation:

Total time=12×32

Step 6: Calculate the total time
Now, we can calculate:

12×32=12×1.5=18 days

Final Answer
C can complete the whole work in 18 days.

---

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    If Rohit alone can complete one-fourth of a work in 32 days, then in how many days Rohit alone can complete the whole work?

    A96 days
    B128 days
    C64 days
    D118 days
  • Question 2 - Select One

    A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?

    A60 days
    B36 days
    C45 days
    D24 days
  • Question 3 - Select One

    P and Q together can complete a work in 20 days. If P alone can complete the same work in 36 days, then in how many days Q alone can complete the same work?

    A48 days
    B42 days
    C45 days
    D51 days