If C alone can complete two-third part of a work in 12 days, then in how many days C can complete the whole work?
24 days
15 days
8 days
18 days
The correct Answer is:B
To solve the problem step by step, we will use the information given about C's work rate.
Step 1: Understand the given information
C can complete two-thirds (2/3) of the work in 12 days.
Step 2: Determine the time taken to complete the whole work
We need to find out how many days C would take to complete the entire work (1 whole work).
Step 3: Use the formula for work completion
The formula to find the time taken to complete the whole work when a person can complete a fraction of the work in a certain number of days is:
Total time=Days taken×Total workPart of work completed
In this case:
- Days taken = 12 days
- Part of work completed = 2/3
- Total work = 1 (whole work)
Step 4: Substitute the values into the formula
We can substitute the values into the formula:
Total time=12×123
Step 5: Simplify the expression
To simplify 123, we can multiply by the reciprocal:
123=32
Now substituting this back into the equation:
Total time=12×32
Step 6: Calculate the total time
Now, we can calculate:
12×32=12×1.5=18 days
Final Answer
C can complete the whole work in 18 days.
---
C can complete two-thirds (2/3) of the work in 12 days.
We need to find out how many days C would take to complete the entire work (1 whole work).
The formula to find the time taken to complete the whole work when a person can complete a fraction of the work in a certain number of days is:
- Days taken = 12 days
- Part of work completed = 2/3
- Total work = 1 (whole work)
We can substitute the values into the formula:
To simplify 123, we can multiply by the reciprocal:
Now, we can calculate:
C can complete the whole work in 18 days.
Similar Questions
Knowledge Check
If Rohit alone can complete one-fourth of a work in 32 days, then in how many days Rohit alone can complete the whole work?
A96 daysB128 daysC64 daysD118 daysA and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
A60 daysB36 daysC45 daysD24 daysP and Q together can complete a work in 20 days. If P alone can complete the same work in 36 days, then in how many days Q alone can complete the same work?
A48 daysB42 daysC45 daysD51 days
A works thrice as much as B. If A can complete this work in 12 days, then in how many days will both A and B complete this work ?
View SolutionA and C started doing a work . After working for 6 days , both left and B alone completed the remaining work in 4 days .In how many days can C alone complete a work in 2 days , then in how many days can A alone complete the work ?
View SolutionU, V and W together can complete a work in 10 days. If U alone can complete the work in 20 days and V alone can complete the work in 30 days, then in how many days W alone can complete the work?
View Solution12 Men can complete one-third of the work in 8 days. In how many days can 16 men complete that work?
View SolutionC alone can complete a work in 20 days and D alone can complete the same workin 30 days. In how many days C and D together can complete the same work?
View Solution