K alone can complete a work in 20 days and M alone can complete the same work in 30 days. K and M start the work together but K leaves the work after 5 days of the starting of work. In how many days M will complete the remaining work?
352 days
252 days
552 days
452 days
The correct Answer is:A
To solve the problem, we will follow these steps:
Step 1: Determine the work done by K and M in one day.
- K can complete the work in 20 days, so K's work in one day = 1/20 of the work.
- M can complete the work in 30 days, so M's work in one day = 1/30 of the work.
Step 2: Calculate the combined work done by K and M in one day.
- Combined work done by K and M in one day = (1/20 + 1/30).
- To add these fractions, we need a common denominator. The LCM of 20 and 30 is 60.
- K's work in one day = 3/60 and M's work in one day = 2/60.
- Therefore, combined work = (3/60 + 2/60) = 5/60 = 1/12 of the work.
Step 3: Calculate the work done by K and M together in the first 5 days.
- Work done in 5 days = 5 * (1/12) = 5/12 of the work.
Step 4: Determine the remaining work after 5 days.
- Total work = 1 (whole work).
- Remaining work = 1 - 5/12 = 7/12 of the work.
Step 5: Calculate how long it will take M to complete the remaining work.
- M's work in one day = 1/30 of the work.
- To find the time taken by M to complete the remaining work (7/12), we use the formula:
Time=Remaining workM's work in one day=7/121/30
- This simplifies to:
Time=712×30=21012=17.5 days
Final Answer:
M will complete the remaining work in 17.5 days.
---
- K can complete the work in 20 days, so K's work in one day = 1/20 of the work.
- M can complete the work in 30 days, so M's work in one day = 1/30 of the work.
- Combined work done by K and M in one day = (1/20 + 1/30).
- To add these fractions, we need a common denominator. The LCM of 20 and 30 is 60.
- K's work in one day = 3/60 and M's work in one day = 2/60.
- Therefore, combined work = (3/60 + 2/60) = 5/60 = 1/12 of the work.
- Work done in 5 days = 5 * (1/12) = 5/12 of the work.
- Total work = 1 (whole work).
- Remaining work = 1 - 5/12 = 7/12 of the work.
- M's work in one day = 1/30 of the work.
- To find the time taken by M to complete the remaining work (7/12), we use the formula:
Time=Remaining workM's work in one day=7/121/30
- This simplifies to:
Time=712×30=21012=17.5 days
M will complete the remaining work in 17.5 days.
Similar Questions
A can complete a work in 20 days & B can complete the same work in 25 days. If they start the work together but After 5 days A left the work . In how many days the total work would be finished ?
View SolutionBoth X and Y together can complete a work in 12 days and Y alone can complete the same work in 30 days. In how many days will X alone complete the work?
View Solution
Knowledge Check
- Question 1 - Select One
P alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed
A9 daysB14 daysC12 daysD18 days - Question 2 - Select One
F alone can complete a work in 24 days and G alone can complete the same work in 32 days. F and G start the work together but G leaves the work 8 days before the completion of work. In how many days the total work will be completed?
A1305 daysB1067 daysC1147 daysD1207 days - Question 3 - Select One
C alone can complete a work in 20 days and D alone can complete the same workin 30 days. In how many days C and D together can complete the same work?
A6 daysB12 daysC15 daysD8 days
A alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?
View SolutionA alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?
View SolutionA alone can complete a work in 10 days and B alone can complete the same work in 20 days. In how many days both 4 and B together can complete half of the total work?
View SolutionBoth A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
View SolutionBoth A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
View Solution