If A can do a work in 5 days and B can do a same work in 6 days. if both work together find how many days they complete the work.?
25/11 days
28/11 days
30/11 days
11/30 days
The correct Answer is:B
To solve the problem of how long A and B will take to complete the work together, we can follow these steps:
Step 1: Determine the work rates of A and B
- A can complete the work in 5 days.
- B can complete the work in 6 days.
Step 2: Calculate the work done by A and B in one day
- The work rate of A (work done by A in one day) = 15 (since A completes the work in 5 days).
- The work rate of B (work done by B in one day) = 16 (since B completes the work in 6 days).
Step 3: Add the work rates of A and B
- Together, their combined work rate = 15+16.
Step 4: Find a common denominator to add the fractions
- The least common multiple (LCM) of 5 and 6 is 30.
- Convert 15 and 16 to have a common denominator of 30:
- 15=630
- 16=530
Step 5: Add the fractions
- Now add the two fractions:
630+530=1130
Step 6: Calculate the time taken to complete the work together
- The combined work rate 1130 means that together, A and B can complete 1130 of the work in one day.
- To find out how many days they will take to complete the entire work, take the reciprocal of their combined work rate:
Time taken=3011 days
Conclusion
- Therefore, A and B together will complete the work in 3011 days.
Final Answer
- The answer is 3011 days or approximately 2.73 days.
---
- A can complete the work in 5 days.
- B can complete the work in 6 days.
- The work rate of A (work done by A in one day) = 15 (since A completes the work in 5 days).
- The work rate of B (work done by B in one day) = 16 (since B completes the work in 6 days).
- Together, their combined work rate = 15+16.
- The least common multiple (LCM) of 5 and 6 is 30.
- Convert 15 and 16 to have a common denominator of 30:
- 15=630
- 16=530
- Now add the two fractions:
630+530=1130
- The combined work rate 1130 means that together, A and B can complete 1130 of the work in one day.
- To find out how many days they will take to complete the entire work, take the reciprocal of their combined work rate:
Time taken=3011 days
- Therefore, A and B together will complete the work in 3011 days.
- The answer is 3011 days or approximately 2.73 days.
Similar Questions
If A can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days , then working together , how many days will they take to complete the work ?
View SolutionIf A can do a work in 10 days and B can do the same work in 15 days, then how many days will they take to complete the work both while working together?
View Solution
Knowledge Check
- Question 1 - Select One
If A alone can do a work in 12 days and B alone can do it in 8 days, Working together, in how many days will they complete it?
A445 daysB4 daysC345 daysD6 days - Question 2 - Select One
A can do a work in 40 days and B can do the same work in 60 days. In how many days they can do it together?
A12B10C15D24 - Question 3 - Select One
A can do a work in 15 days and B can do the same in 25 days. If they start the work together and B leaves 7 days before completion of the work then the work will be completed in how many days?
A12 daysB8 daysC9 daysD1012 days
A can do a work in x days while B can do the same work in y days then in how many days will they complete the work, working together?
View SolutionA can do a work in 4 days while B can do that same work in 6 days. If they worked together, then that work would be completed in
View SolutionA can do a work in 36 days and B in 12 days. If they work on it together, then in how many days will they be able to do the work?
View SolutionP can do a piece of work in 25 days and Q can do the same work in 15 days. In how many days they can complete the work by working together?
View SolutionP can do a piece of work in 25 days and Q can do the same work in 15 days. In how many days they can complete the work by working together?
View Solution