If 10 men can complete a piece of work in 12 days by working 7 hours a day, then in how many days can 14 mendo the same work by working 6 hours a day?
A. 16
B. 15
C. 10
D. 12
The correct Answer is:C
To solve the problem step by step, we can use the concept of work done, which is represented by the formula:
Work=Men×Days×Hours
Step 1: Calculate the total work done by 10 men in 12 days working 7 hours a day.
Using the formula:
Total Work=Men×Days×Hours
Substituting the values:
Total Work=10men×12days×7hours=840man-hours
Step 2: Set up the equation for the new scenario with 14 men working 6 hours a day.
Let D be the number of days required for 14 men to complete the same work while working 6 hours a day. The equation will be:
Total Work=14men×Ddays×6hours
Step 3: Equate the total work from both scenarios.
Since the total work remains the same, we can set the two expressions for total work equal to each other:
840man-hours=14men×Ddays×6hours
Step 4: Simplify the equation to find D.
First, calculate 14×6:
14×6=84
Now we can rewrite the equation:
840=84D
To find D, divide both sides by 84:
D=84084=10
Conclusion:
The number of days required for 14 men to complete the work by working 6 hours a day is 10 days.
---
Similar Questions
If 25 men can do a piece of work in 36 days working 10 hours a day, then how many men are required to complete the work working 6 hours a day in 20 days?
View SolutionIf 10 men complete half work in 12 days when they work 8 hours per day, In how many days 18 men complete the full when they work 6 hours/day ?
View Solution
Knowledge Check
- Question 1 - Select One
If 15 men can complete a work in 16 days by working 8 hours daily, then in how many days will 10 men complete the work by working 12 hours daily?
Aa) 15Bb) 12Cc) 10Dd) 16 - Question 2 - Select One
If 20 men complete a work in 56 days by working 10 hours a day how many days will 40 men take to complete the same work by working 8 hours a day?
A30B25C48D35 - Question 3 - Select One
If 4 men can reap a field in 5 days working 12 hours a day, in how many days can 10 men reap the same field working 8 hours a day?
A3B2C4D6
Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View SolutionFifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View SolutionWorking 7 hours a day, 18 persons can complete a certain work in 32 days. In how many days would 14 persons complete the same work, working 8 hours a day ?
View Solution38 men can complete a work by working 6 Hrs per day in 12 days then calculate in how many days 51 men can do double of the work by work ing 8 hrs per day?
View Solution15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
View Solution