The efficiency of A is thrice as that of B and efficiency of B is twice as that of C. If B alone can finish a work in 15 days, in how many days A and C together will complete that work?
4(27)
6(12)
7(45)
4(13)
The correct Answer is:A
To solve the problem step by step, let's break it down:
Step 1: Understand the efficiency relationships
We are given:
- The efficiency of A is thrice that of B.
- The efficiency of B is twice that of C.
Let the efficiency of C be x. Then:
- The efficiency of B will be 2x (since B is twice as efficient as C).
- The efficiency of A will be 3×(2x)=6x (since A is thrice as efficient as B).
Step 2: Calculate the total work
We know that B can finish the work in 15 days. The total work can be calculated using the formula:
Total Work=Efficiency×Time
Since B's efficiency is 2x and it takes 15 days, we have:
Total Work=2x×15=30x
Step 3: Calculate the combined efficiency of A and C
The combined efficiency of A and C is:
Efficiency of A+Efficiency of C=6x+x=7x
Step 4: Calculate the time taken by A and C together to complete the work
Using the total work calculated in Step 2 and the combined efficiency from Step 3, we can find the time taken by A and C together:
Time=Total WorkCombined Efficiency=30x7x
The x cancels out:
Time=307 days
Conclusion
A and C together will complete the work in 307 days, which is approximately 427 days.
We are given:
- The efficiency of A is thrice that of B.
- The efficiency of B is twice that of C.
- The efficiency of B will be 2x (since B is twice as efficient as C).
- The efficiency of A will be 3×(2x)=6x (since A is thrice as efficient as B).
We know that B can finish the work in 15 days. The total work can be calculated using the formula:
Total Work=Efficiency×Time
Since B's efficiency is 2x and it takes 15 days, we have:
Total Work=2x×15=30x
The combined efficiency of A and C is:
Efficiency of A+Efficiency of C=6x+x=7x
Using the total work calculated in Step 2 and the combined efficiency from Step 3, we can find the time taken by A and C together:
Time=Total WorkCombined Efficiency=30x7x
The x cancels out:
Time=307 days
A and C together will complete the work in 307 days, which is approximately 427 days.
Similar Questions
Knowledge Check
- Question 1 - Select One
A is twice as efficient as B and together they finish a piece of work in 18 days. How many days will A take to complete the work alone?
A27B24C36D42 - Question 2 - Select One
A is 40% more efficient than B and C is 20% less efficient than B. Working together, they can finish a work is 5 days. In how many days will A alone complete 70% that work?
A9B7C10D8 - Question 3 - Select One
A is 40% more efficient than B and C is 20% less efficient than B. Working together, they can finish a work is 5 days. In how many days will A alone complete 70% of that work?
A9B7C10D8
A is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?
View SolutionBy working together, A and B can finish a work in 15 days. If B alone can finish the work in 20 days, in how many days can A alone finish the work?
View SolutionBy working together, A and B can finish a work in 15 days. If B alone can finish the work in 20 days, in how many days can A alone finish the work?
View SolutionB is twice as efficients as A, who works half as fast as C. If, A, B and C can complete a piece of work in 20 days. In how may day can B and C together complete it?
View SolutionA is twice as fast a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work ?
View Solution