Doubtnut Promotions Sticky

A and B together can complete a task in 1.2 days. However, if A works alone, completes half the job and leaves and 8 then B works alone and completes the rest of the work, it takes 2.5 days in all to complete the work. If B is more efficient than A, how many days would it have taken B to do the work by herself?

A

1.5

B

1.8

C

2.0

D

2.2

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will use the information given in the question about A and B's work rates and the total time taken to complete the task.

Step 1: Define Variables
Let:
- A's time to complete the work alone = x days
- B's time to complete the work alone = y days

Step 2: Write the Work Rate Equation
From the information that A and B together can complete the task in 1.2 days, we can express their combined work rate:
1x+1y=11.2
This can be rewritten as:
1x+1y=56
Multiplying through by xy gives:
y+x=5xy6(Equation 1)

Step 3: Analyze the Work Done
A completes half the job and then leaves. The time taken by A to complete half the job is:
x2 days
After A leaves, B completes the remaining half of the job. The time taken by B to complete half the job is:
y2 days
The total time taken to complete the work is given as 2.5 days:
x2+y2=2.5
Multiplying through by 2 gives:
x+y=5(Equation 2)

Step 4: Solve the Equations
Now we have two equations:
1. x+y=5xy6
2. x+y=5

From Equation 2, we can substitute x+y in Equation 1:
5=5xy6
Multiplying both sides by 6 gives:
30=5xy
Dividing by 5 gives:
xy=6(Equation 3)

Step 5: Substitute and Solve for x and y
Now we can use Equation 2 and Equation 3 to find x and y. From Equation 2:
y=5x
Substituting this into Equation 3:
x(5x)=6
Expanding gives:
5xx2=6
Rearranging gives:
x25x+6=0

Step 6: Factor the Quadratic
Factoring the quadratic:
(x2)(x3)=0
Thus, x=2 or x=3.

Step 7: Find Corresponding y Values
Using y=5x:
- If x=2, then y=3.
- If x=3, then y=2.

Step 8: Determine the More Efficient Worker
Since it is given that B is more efficient than A, we conclude:
- If y=3 (B takes 3 days), then x=2 (A takes 2 days).
- If y=2 (B takes 2 days), then x=3 (A takes 3 days).

Thus, B must take 2 days to complete the work alone.

Final Answer
B would take 2 days to complete the work by herself.

---

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B together can complete a particular task in 8 days. If
    B alone can complete the same task in 10 days, how many
    days will A take to complete the task if he works alone ?

    A28
    B36
    C40
    D32
  • Question 2 - Select One

    Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?

    A30
    B50
    C45
    D42
  • Question 3 - Select One

    Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?

    A30
    B50
    C45
    D42