A and B together can complete a task in 1.2 days. However, if A works alone, completes half the job and leaves and 8 then B works alone and completes the rest of the work, it takes 2.5 days in all to complete the work. If B is more efficient than A, how many days would it have taken B to do the work by herself?
1.5
1.8
2.0
2.2
The correct Answer is:C
To solve the problem step by step, we will use the information given in the question about A and B's work rates and the total time taken to complete the task.
Step 1: Define Variables
Let:
- A's time to complete the work alone = x days
- B's time to complete the work alone = y days
Step 2: Write the Work Rate Equation
From the information that A and B together can complete the task in 1.2 days, we can express their combined work rate:
1x+1y=11.2
This can be rewritten as:
1x+1y=56
Multiplying through by xy gives:
y+x=5xy6(Equation 1)
Step 3: Analyze the Work Done
A completes half the job and then leaves. The time taken by A to complete half the job is:
x2 days
After A leaves, B completes the remaining half of the job. The time taken by B to complete half the job is:
y2 days
The total time taken to complete the work is given as 2.5 days:
x2+y2=2.5
Multiplying through by 2 gives:
x+y=5(Equation 2)
Step 4: Solve the Equations
Now we have two equations:
1. x+y=5xy6
2. x+y=5
From Equation 2, we can substitute x+y in Equation 1:
5=5xy6
Multiplying both sides by 6 gives:
30=5xy
Dividing by 5 gives:
xy=6(Equation 3)
Step 5: Substitute and Solve for x and y
Now we can use Equation 2 and Equation 3 to find x and y. From Equation 2:
y=5−x
Substituting this into Equation 3:
x(5−x)=6
Expanding gives:
5x−x2=6
Rearranging gives:
x2−5x+6=0
Step 6: Factor the Quadratic
Factoring the quadratic:
(x−2)(x−3)=0
Thus, x=2 or x=3.
Step 7: Find Corresponding y Values
Using y=5−x:
- If x=2, then y=3.
- If x=3, then y=2.
Step 8: Determine the More Efficient Worker
Since it is given that B is more efficient than A, we conclude:
- If y=3 (B takes 3 days), then x=2 (A takes 2 days).
- If y=2 (B takes 2 days), then x=3 (A takes 3 days).
Thus, B must take 2 days to complete the work alone.
Final Answer
B would take 2 days to complete the work by herself.
---
Let:
- A's time to complete the work alone = x days
- B's time to complete the work alone = y days
From the information that A and B together can complete the task in 1.2 days, we can express their combined work rate:
1x+1y=11.2
This can be rewritten as:
1x+1y=56
Multiplying through by xy gives:
y+x=5xy6(Equation 1)
A completes half the job and then leaves. The time taken by A to complete half the job is:
x2 days
After A leaves, B completes the remaining half of the job. The time taken by B to complete half the job is:
y2 days
The total time taken to complete the work is given as 2.5 days:
x2+y2=2.5
Multiplying through by 2 gives:
x+y=5(Equation 2)
Now we have two equations:
1. x+y=5xy6
2. x+y=5
5=5xy6
Multiplying both sides by 6 gives:
30=5xy
Dividing by 5 gives:
xy=6(Equation 3)
Now we can use Equation 2 and Equation 3 to find x and y. From Equation 2:
y=5−x
Substituting this into Equation 3:
x(5−x)=6
Expanding gives:
5x−x2=6
Rearranging gives:
x2−5x+6=0
Factoring the quadratic:
(x−2)(x−3)=0
Thus, x=2 or x=3.
Using y=5−x:
- If x=2, then y=3.
- If x=3, then y=2.
Since it is given that B is more efficient than A, we conclude:
- If y=3 (B takes 3 days), then x=2 (A takes 2 days).
- If y=2 (B takes 2 days), then x=3 (A takes 3 days).
B would take 2 days to complete the work by herself.
Similar Questions
A and B together can complete a task in 12 days. However, if A works alone, completes half the job and leaves and then B works alone and completes the rest of the work, it takes 25 days in all to complete the work. If B is more efficient than A, how many days would it have taken B to do the work by herself?
View SolutionA and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?
View Solution
Knowledge Check
- Question 1 - Select One
A and B together can complete a particular task in 8 days. If
B alone can complete the same task in 10 days, how many
days will A take to complete the task if he works alone ?A28B36C40D32 - Question 2 - Select One
Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
A30B50C45D42 - Question 3 - Select One
Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
A30B50C45D42
A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
View SolutionA and B together can complete a work in 35 days while A alone can complete the same work in 60 days. In how many days, B alone will be able to complete the same work?
View SolutionA and B together can complete a piece of work in 12 days. They worked together for 5 days and then A alone finished the rest of the work in 14 days. A alone can complete the work in
View SolutionA and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
View SolutionA alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?
View Solution