A can finish 80% of a task in 12 days and B can finish 20% of the same task in 2 days. They started the task together, but B left after 2 days and A continued to work. In how many days was the entire task completed?
17.5
10
15
12
The correct Answer is:D
Step by step video, text & image solution for A can finish 80% of a task in 12 days and B can finish 20% of the same task in 2 days. They started the task together, but B left after 2 days and A continued to work. In how many days was the entire task completed? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Related Playlists
- BOOK - SSC SELECTION POSTCHAPTER - SSC PREVIOUS YEAR PAPER MATRIX LEVEL 15 OCTOBER 2019EXERCISE - Quantitative Aptitude Basic Arithmetic Skill25videos
SSC PREVIOUS YEAR PAPER MATRIX LEVEL 15 OCTOBER 2019
- BOOK - SSC SELECTION POSTCHAPTER - SSC SELECTION POST (14 DEC 2020) SHIFT 1 MATRICULATION LEVEL EXERCISE - Quantitative Aptitude25videos
SSC SELECTION POST (14 DEC 2020) SHIFT 1 MATRICULATION LEVEL
Knowledge Check
- Question 1 - Select One
A can do 40% of a work in 6 days and B can do 30% of the same work in 3 days. They started the work together but B left after 2 days and A continued to work. In how many days was the entire work completed ?
A किसी कार्य का 40% भाग 6 दिनों में तथा B इसी कार्य का 30% भाग 3 दिनों में पूरा कर सकता है | उन्होंने एक साथ कार्य शुरू किया लेकिन 2 दिनों के बाद B हट गया और A ने कार्य जारी रखा | पूरा कार्य कितने दिनों में समाप्त हुआ ?A10B12C9D15 - Question 1 - Select One
A can finish work in 20 days and B can finish the same work in 25 days. They began together, but B left the work after 5 days. How many more days will A take to finish the remaining work?
A 20 दिनों में कार्य समाप्त कर सकता है तथा B इसी कार्य को 25 दिनों में पूरा कर सकता है | उन्होंने एक साथ कार्य करना शुरू किया, लेकिन B ने 5 दिनों के बाद कार्य छोड़ दिया | शेष कार्य पूरा करने में A को कितने अतिरिक्त दिन लगेंगे ?A16B8C21D11 - Question 1 - Select One
A can finish 35 of a task in 6 days and B can finish 23 of the same task in 12 days. A and B worked together for 5 days. C alone completed the remaining task in 8 days. If B and C working together will complete the same task in:
A10 daysB18 daysC12 daysD15 days - Question 1 - Select One
A can finish 25 of a task in 12 days and B can finish 23 of the same task in 30 days. They work together for 10 days. C alone completes the remaining task in 16 days. B and C together will complete 45 of the same task in:
A16 daysB12 daysC20 daysD15 days - Question 1 - Select One
A can finish a task in 45 days and B can finish the same task in 30 days. They work together for 3 days and then A leaves. In how many days will B finish the remaining task?
A5B18C25D20 - Question 1 - Select One
A can finish 25 of a task in 12 days and B can finish 23 of the same task in 30 days .They work together for 10 days .C alone completes the remaining task remaining task in 16 days .B and C together will complete 45 of the same task in :
A16 daysB12 daysC20 daysD15 days - Question 1 - Select One
A can do a work in 10 days and B can do the same in 20 days. If they start the work together and A leaves that work 5 days before completion, in how many days the work will be finished?
A10B8C12D9 - Question 1 - Select One
Working for 9 hours a day. X can finish a task in 3 days, Y can finish three times of the same task in 8 days, and Z can finish five times of the same task in 12 days. Working together, in how many hours will they complete the task?
A12B8C10D9
Similar Questions
A can finish 25% of a task in 3 days and B can finish half of the task in 18 days. If they work on it together, in how many days can they finish the task?
View SolutionA can complete a work in 20 days & B can complete the same work in 25 days. If they start the work together but After 5 days A left the work . In how many days the total work would be finished ?
View Solution